CONSTRUCTION METHOD OF BUOYANCY-TYPE BASE ISOLATED FOUNDATION STRUCTURE, AND BUOYANCY-TYPE BASE ISOLATED FOUNDATION STRUCTURE
PROBLEM TO BE SOLVED: To provide a construction method of a buoyancy-type base isolated foundation structure in which a frictional force is reduced by using buoyancy and a structure of permitting slippage is formed, and thereby the structure where the earthquake load higher than a setting level may not be transmitted to a construction can be formed to exhibit a superior base isolation effect.SOLUTION: A construction method of a buoyancy-type base isolated foundation structure is provided which includes: a step of excavating the ground and constructing a foundation pit 2; a step of disposing a construction 3 in the bottom face 2a of the foundation pit 2; and a step of storing a fluid 4 in the foundation pit 2. In the storage step of the fluid, a target value of an inertial force α acting on the construction 3 in an earthquake is set; the buoyancy V necessary for the construction 3 is calculated based on V=W-F/μ representing a relationship of a ground force N of the construction 3, a load W of the construction 3 and a horizontal force F(=m/α) to act on construction 3 in the earthquake; and a water-level of the fluid 4 is adjusted based on the calculated buoyancy V.SELECTED DRAWING: Figure 1
【課題】浮力を利用して摩擦力を低減しすべりを許容する構造とすることで、設定レベル以上の地震力が構造物に伝達されない構造となり、優れた免震効果を発揮することができる。【解決手段】地盤を掘削して基礎ピット2を構築する工程と、基礎ピット2の底面2aに構造物3を配置する工程と、基礎ピット2内に流体4を貯留する工程と、を有し、流体の貯留工程では、地震時に構造物3に作用する慣性力αの目標値を設定し、構造物3の接地力Nと、構造物3の荷重Wと、地震時に構造物3に作用する水平力F(=m・α)と、の関係を示すV=W−F/μに基づいて、構造物3に必要な浮力Vを算出し、算出された浮力Vに基づいて流体4の水位が調整される浮力式免震基礎構造の構築方法を提供する。【選択図】図1
CONSTRUCTION METHOD OF BUOYANCY-TYPE BASE ISOLATED FOUNDATION STRUCTURE, AND BUOYANCY-TYPE BASE ISOLATED FOUNDATION STRUCTURE
PROBLEM TO BE SOLVED: To provide a construction method of a buoyancy-type base isolated foundation structure in which a frictional force is reduced by using buoyancy and a structure of permitting slippage is formed, and thereby the structure where the earthquake load higher than a setting level may not be transmitted to a construction can be formed to exhibit a superior base isolation effect.SOLUTION: A construction method of a buoyancy-type base isolated foundation structure is provided which includes: a step of excavating the ground and constructing a foundation pit 2; a step of disposing a construction 3 in the bottom face 2a of the foundation pit 2; and a step of storing a fluid 4 in the foundation pit 2. In the storage step of the fluid, a target value of an inertial force α acting on the construction 3 in an earthquake is set; the buoyancy V necessary for the construction 3 is calculated based on V=W-F/μ representing a relationship of a ground force N of the construction 3, a load W of the construction 3 and a horizontal force F(=m/α) to act on construction 3 in the earthquake; and a water-level of the fluid 4 is adjusted based on the calculated buoyancy V.SELECTED DRAWING: Figure 1
【課題】浮力を利用して摩擦力を低減しすべりを許容する構造とすることで、設定レベル以上の地震力が構造物に伝達されない構造となり、優れた免震効果を発揮することができる。【解決手段】地盤を掘削して基礎ピット2を構築する工程と、基礎ピット2の底面2aに構造物3を配置する工程と、基礎ピット2内に流体4を貯留する工程と、を有し、流体の貯留工程では、地震時に構造物3に作用する慣性力αの目標値を設定し、構造物3の接地力Nと、構造物3の荷重Wと、地震時に構造物3に作用する水平力F(=m・α)と、の関係を示すV=W−F/μに基づいて、構造物3に必要な浮力Vを算出し、算出された浮力Vに基づいて流体4の水位が調整される浮力式免震基礎構造の構築方法を提供する。【選択図】図1
CONSTRUCTION METHOD OF BUOYANCY-TYPE BASE ISOLATED FOUNDATION STRUCTURE, AND BUOYANCY-TYPE BASE ISOLATED FOUNDATION STRUCTURE
浮力式免震基礎構造の構築方法、および浮力式免震基礎構造
TAJI YOICHI (Autor:in) / FUKUTAKE TAKEYOSHI (Autor:in) / HASEBE MASANOBU (Autor:in) / ASAKA MIHARU (Autor:in) / SHAMOTO YASUHIRO (Autor:in)
21.04.2016
Patent
Elektronische Ressource
Japanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
CONSTRUCTION METHOD OF BASE-ISOLATED FOUNDATION STRUCTURE
Europäisches Patentamt | 2016
|Buoyancy compensation type combined foundation and construction method
Europäisches Patentamt | 2021
|Wide-surface inclined buoyancy self-release foundation structure and construction method thereof
Europäisches Patentamt | 2024
|