SEISMIC ISOLATOR EXCHANGE STRUCTURE AND SEISMIC ISOLATOR EXCHANGE METHOD
PROBLEM TO BE SOLVED: To enable a seismic isolator supporting column to be exchanged by jacking-up a steel beam connected to a column at a desired position from the column.SOLUTION: This invention relates to a seismic isolator exchange structure having a seismic isolator 16 supporting a column 14 to which a steel beam 22 is connected and a load receiving beam 20 fixed to a side surface of the beam, protruded out of the side surface, and supported by a jack and a seismic isolator exchange method for exchanging the seismic isolator supporting the column to which the steel beam is connected, the method comprising the steps of protruding out of a side surface and fixing the load receiving beam 20 to the side surface of the beam; supporting the load receiving beam with a jack 60; and jacking-up the load receiving beam with the jack and exchanging the seismic isolator.SELECTED DRAWING: Figure 1
【課題】柱に接合された鋼製の梁を柱からの所望位置でジャッキアップすることによって、柱を支持する免震装置を交換できる。【解決手段】鋼製の梁22が接合された柱14を支持する免震装置16と、前記梁の側面に取り付けられて前記側面から張り出し、ジャッキにより支持される荷重受梁20と、を有する免震装置交換構造、及び、鋼製の梁が接合された柱を支持する免震装置を交換する免震装置交換方法において、前記梁の側面に前記側面から張り出して荷重受梁20を取り付ける工程と、前記荷重受梁をジャッキ60で支持する工程と、前記荷重受梁を前記ジャッキでジャッキアップし、前記免震装置を交換する工程と、を有する。【選択図】図1
SEISMIC ISOLATOR EXCHANGE STRUCTURE AND SEISMIC ISOLATOR EXCHANGE METHOD
PROBLEM TO BE SOLVED: To enable a seismic isolator supporting column to be exchanged by jacking-up a steel beam connected to a column at a desired position from the column.SOLUTION: This invention relates to a seismic isolator exchange structure having a seismic isolator 16 supporting a column 14 to which a steel beam 22 is connected and a load receiving beam 20 fixed to a side surface of the beam, protruded out of the side surface, and supported by a jack and a seismic isolator exchange method for exchanging the seismic isolator supporting the column to which the steel beam is connected, the method comprising the steps of protruding out of a side surface and fixing the load receiving beam 20 to the side surface of the beam; supporting the load receiving beam with a jack 60; and jacking-up the load receiving beam with the jack and exchanging the seismic isolator.SELECTED DRAWING: Figure 1
【課題】柱に接合された鋼製の梁を柱からの所望位置でジャッキアップすることによって、柱を支持する免震装置を交換できる。【解決手段】鋼製の梁22が接合された柱14を支持する免震装置16と、前記梁の側面に取り付けられて前記側面から張り出し、ジャッキにより支持される荷重受梁20と、を有する免震装置交換構造、及び、鋼製の梁が接合された柱を支持する免震装置を交換する免震装置交換方法において、前記梁の側面に前記側面から張り出して荷重受梁20を取り付ける工程と、前記荷重受梁をジャッキ60で支持する工程と、前記荷重受梁を前記ジャッキでジャッキアップし、前記免震装置を交換する工程と、を有する。【選択図】図1
SEISMIC ISOLATOR EXCHANGE STRUCTURE AND SEISMIC ISOLATOR EXCHANGE METHOD
免震装置交換構造、及び免震装置交換方法
CHO SHISHUN (Autor:in) / NOZAWA HIROKAZU (Autor:in) / OKUDE HISATO (Autor:in)