JUNCTION STRUCTURE OF FLOOR JOIST
PROBLEM TO BE SOLVED: To provide a junction structure of a floor joist in which restraint is enhanced when a floor joist is temporarily supported, with improved efficiency in lifting work with the floor joist.SOLUTION: A junction structure 1 of a floor joist according to the present invention is provided at a building, and includes a floor joist 2 in which a flange 21 and a web 24 are formed, a connection member 4 which is attached to a peripheral member 3 to which the floor joist 2 is jointed. In the connection member 4, a pair of side plates 41 protruding from the peripheral member 3 are formed, the pair of side plates 41 are separated from each other to form a gap S, and further, a pair of pinching parts 42 extending from each of the pair of side plates 41 to approach each other are formed, and under a condition in which the web 24 of the floor joist 2 is inserted in the gap S, the web 24 of the floor joist 2 is pinched by the pair of pinching parts 42.SELECTED DRAWING: Figure 3
【課題】床根太を仮支持したときの拘束力を高めるとともに、床根太の揚重作業の効率性を向上させた床根太の接合構造を提供する。【解決手段】本発明を適用した床根太の接合構造1は、建築物に設けられるものであり、フランジ21及びウェブ24が形成された床根太2と、床根太2が接合される周囲部材3に取り付けられる接続部材4とを備える。接続部材4は、周囲部材3から突出する一対の側板41が形成されて、一対の側板41を互いに離間させることで隙間Sが形成されるとともに、一対の側板41の各々から互いに接近するように延びる一対の挟持部42が形成されて、床根太2のウェブ24が隙間Sに挿通された状態で、床根太2のウェブ24が一対の挟持部42で挟まれる。【選択図】図3
JUNCTION STRUCTURE OF FLOOR JOIST
PROBLEM TO BE SOLVED: To provide a junction structure of a floor joist in which restraint is enhanced when a floor joist is temporarily supported, with improved efficiency in lifting work with the floor joist.SOLUTION: A junction structure 1 of a floor joist according to the present invention is provided at a building, and includes a floor joist 2 in which a flange 21 and a web 24 are formed, a connection member 4 which is attached to a peripheral member 3 to which the floor joist 2 is jointed. In the connection member 4, a pair of side plates 41 protruding from the peripheral member 3 are formed, the pair of side plates 41 are separated from each other to form a gap S, and further, a pair of pinching parts 42 extending from each of the pair of side plates 41 to approach each other are formed, and under a condition in which the web 24 of the floor joist 2 is inserted in the gap S, the web 24 of the floor joist 2 is pinched by the pair of pinching parts 42.SELECTED DRAWING: Figure 3
【課題】床根太を仮支持したときの拘束力を高めるとともに、床根太の揚重作業の効率性を向上させた床根太の接合構造を提供する。【解決手段】本発明を適用した床根太の接合構造1は、建築物に設けられるものであり、フランジ21及びウェブ24が形成された床根太2と、床根太2が接合される周囲部材3に取り付けられる接続部材4とを備える。接続部材4は、周囲部材3から突出する一対の側板41が形成されて、一対の側板41を互いに離間させることで隙間Sが形成されるとともに、一対の側板41の各々から互いに接近するように延びる一対の挟持部42が形成されて、床根太2のウェブ24が隙間Sに挿通された状態で、床根太2のウェブ24が一対の挟持部42で挟まれる。【選択図】図3
JUNCTION STRUCTURE OF FLOOR JOIST
床根太の接合構造
NAKAYASU MASAAKI (Autor:in) / SHISHIDO TADAKAZU (Autor:in) / KAWAI YOSHIMICHI (Autor:in) / AZUMA SEIZABURO (Autor:in) / SHIMIZU NOBUTAKA (Autor:in) / SATO KEIICHI (Autor:in)
22.06.2017
Patent
Elektronische Ressource
Japanisch
IPC:
E04B
Allgemeine Baukonstruktionen
,
GENERAL BUILDING CONSTRUCTIONS
CONNECTION MEMBER AND JUNCTION STRUCTURE OF FLOOR JOIST