CONSTRUCTION METHOD OF STRUCTURE, AND WORK BARGE
PROBLEM TO BE SOLVED: To provide a construction method of a structure and a work barge for stably towing and installing on a water bottom a large structure that exceeds hoisting capacity of a crane carried on a ship.SOLUTION: A hoisting jig 11 connected to a windmill foundation 1 is connected to a wire 13 of a crane 9 installed on a hull 8 of a work barge 7, and the windmill foundation 1 is hung by the crane 9. The windmill foundation 1 is placed inside a construction scaffold 17 of a frame structure installed on the hull 8, using the crane 9. After connecting a counterweight 23 installed on a perpendicular frame 21 of the construction scaffold 17 with the hoisting jig 11 using a wire 25, the wire 13 is removed from the hoisting jig 11 and the counterweight 23 is made to support the windmill foundation 1. Then, the work barge 7 is moved for transporting the windmill foundation 1 to a prescribed water area, the wire 25 is removed from the hoisting jig 11 and the wire 13 is attached, for hoisting the windmill foundation 1 with the crane 9 and submerging the windmill foundation to a water bottom.SELECTED DRAWING: Figure 2
【課題】船に搭載されたクレーンの吊り上げ能力以上の大型の構造物を安定して曳航し、水底に設置できる構造物の施工方法および作業台船を提供する。【解決手段】作業台船7の船体8上に設置されたクレーン9のワイヤ13に風車基礎1に接続した吊り治具11を連結し、クレーン9で風車基礎1を吊り下げる。次に、クレーン9を用いて、船体8上に設置されたフレーム構造の架設用櫓17内に風車基礎1を配置する。そして、架設用櫓17の垂直フレーム21に設置されるカウンターウェイト23と吊り治具11とをワイヤ25で連結した後、ワイヤ13を吊り治具11から取り外してカウンターウェイト23で風車基礎1を支持させる。その後、作業台船7を移動させて風車基礎1を所定の水域に運搬し、吊り治具11からワイヤ25を取り外してワイヤ13を取り付け、風車基礎1をクレーン9で吊り下げて水底に沈める。【選択図】図2
CONSTRUCTION METHOD OF STRUCTURE, AND WORK BARGE
PROBLEM TO BE SOLVED: To provide a construction method of a structure and a work barge for stably towing and installing on a water bottom a large structure that exceeds hoisting capacity of a crane carried on a ship.SOLUTION: A hoisting jig 11 connected to a windmill foundation 1 is connected to a wire 13 of a crane 9 installed on a hull 8 of a work barge 7, and the windmill foundation 1 is hung by the crane 9. The windmill foundation 1 is placed inside a construction scaffold 17 of a frame structure installed on the hull 8, using the crane 9. After connecting a counterweight 23 installed on a perpendicular frame 21 of the construction scaffold 17 with the hoisting jig 11 using a wire 25, the wire 13 is removed from the hoisting jig 11 and the counterweight 23 is made to support the windmill foundation 1. Then, the work barge 7 is moved for transporting the windmill foundation 1 to a prescribed water area, the wire 25 is removed from the hoisting jig 11 and the wire 13 is attached, for hoisting the windmill foundation 1 with the crane 9 and submerging the windmill foundation to a water bottom.SELECTED DRAWING: Figure 2
【課題】船に搭載されたクレーンの吊り上げ能力以上の大型の構造物を安定して曳航し、水底に設置できる構造物の施工方法および作業台船を提供する。【解決手段】作業台船7の船体8上に設置されたクレーン9のワイヤ13に風車基礎1に接続した吊り治具11を連結し、クレーン9で風車基礎1を吊り下げる。次に、クレーン9を用いて、船体8上に設置されたフレーム構造の架設用櫓17内に風車基礎1を配置する。そして、架設用櫓17の垂直フレーム21に設置されるカウンターウェイト23と吊り治具11とをワイヤ25で連結した後、ワイヤ13を吊り治具11から取り外してカウンターウェイト23で風車基礎1を支持させる。その後、作業台船7を移動させて風車基礎1を所定の水域に運搬し、吊り治具11からワイヤ25を取り外してワイヤ13を取り付け、風車基礎1をクレーン9で吊り下げて水底に沈める。【選択図】図2
CONSTRUCTION METHOD OF STRUCTURE, AND WORK BARGE
構造物の施工方法および作業台船
USAMI EIJI (Autor:in) / TAKAHASHI SHINOBU (Autor:in) / FUKUMOTO YUKINARI (Autor:in) / MAEDA OSAMU (Autor:in)
21.09.2017
Patent
Elektronische Ressource
Japanisch
WORK BARGE AND METHOD FOR CONSTRUCTING OFFSHORE STRUCTURE
Europäisches Patentamt | 2018
|Construction work on the New York state barge canal
Engineering Index Backfile | 1900
Form work and timbering details in concrete barge construction
Engineering Index Backfile | 1919
Electricity on Barge canal work