CARRY-IN/OUT METHOD AND CARRY-IN/OUT FACILITY
To allow the carrying-in/out of parts and materials without using a large crane.SOLUTION: A carry-in/out method includes: a support step of supporting, with lifting equipment 14, an existing superstructure member 12 in a prescribed span part region within the same span of a bridge 100; a separation step of separating the existing superstructure member 12, supported by the lifting equipment 14, from the bridge 100; a placing step of placing an object 90 to be transported on the existing superstructure member 12 separated in the separating step; a lifting step of lifting the existing superstructure member 12, on which the object 90 to be transported is placed in the placing step, by the lifting equipment 14; and a carry-out step of carrying out the object 90 to be transported from the top of the existing superstructure member 12 lifted in the lifting step.SELECTED DRAWING: Figure 1
【課題】大型クレーンを使用せずに部材や資機材の搬入出を行えるようにする。【解決手段】橋梁100の同一径間内の所定の支間部領域の既設の上部工部材12を、昇降設備14で支持する支持工程と、昇降設備14で支持した既設の上部工部材12を橋梁100から切り離す切り離し工程と、前記切り離し工程で切り離された既設の上部工部材12の上に運搬対象物90を載置する載置工程と、前記載置工程で運搬対象物90が載置された既設の上部工部材12を、昇降設備14で昇降させる昇降工程と、前記昇降工程で昇降させた既設の上部工部材12の上から、運搬対象物90を運び出す運び出し工程と、を備える。【選択図】図1
CARRY-IN/OUT METHOD AND CARRY-IN/OUT FACILITY
To allow the carrying-in/out of parts and materials without using a large crane.SOLUTION: A carry-in/out method includes: a support step of supporting, with lifting equipment 14, an existing superstructure member 12 in a prescribed span part region within the same span of a bridge 100; a separation step of separating the existing superstructure member 12, supported by the lifting equipment 14, from the bridge 100; a placing step of placing an object 90 to be transported on the existing superstructure member 12 separated in the separating step; a lifting step of lifting the existing superstructure member 12, on which the object 90 to be transported is placed in the placing step, by the lifting equipment 14; and a carry-out step of carrying out the object 90 to be transported from the top of the existing superstructure member 12 lifted in the lifting step.SELECTED DRAWING: Figure 1
【課題】大型クレーンを使用せずに部材や資機材の搬入出を行えるようにする。【解決手段】橋梁100の同一径間内の所定の支間部領域の既設の上部工部材12を、昇降設備14で支持する支持工程と、昇降設備14で支持した既設の上部工部材12を橋梁100から切り離す切り離し工程と、前記切り離し工程で切り離された既設の上部工部材12の上に運搬対象物90を載置する載置工程と、前記載置工程で運搬対象物90が載置された既設の上部工部材12を、昇降設備14で昇降させる昇降工程と、前記昇降工程で昇降させた既設の上部工部材12の上から、運搬対象物90を運び出す運び出し工程と、を備える。【選択図】図1
CARRY-IN/OUT METHOD AND CARRY-IN/OUT FACILITY
搬入出方法および搬入出設備
TANAKA HIROAKI (Autor:in) / NAKAYAMA ATSUO (Autor:in) / NAKAMURA NOBUHIDE (Autor:in)
08.08.2019
Patent
Elektronische Ressource
Japanisch
IPC:
E01D
BRIDGES
,
Brücken