PILE CONSTRUCTION MANAGEMENT METHOD, PILE CONSTRUCTION MANAGEMENT SYSTEM, AND PORTABLE TERMINAL CONSTITUTING PILE CONSTRUCTION MANAGEMENT SYSTEM
To provide a pile construction management method, a pile construction management system, and a portable terminal constituting the pile construction management system, capable of performing construction management on a steel pipe pile while accurately identifying a pile core position of the steel pipe pile in the vicinity of the ground without including any complicated jigs.SOLUTION: A pile construction management system 500 includes: a target 100 fixed on a bracing member 50 or the ground around a steel pipe pile P; a measuring instrument 200 for measuring a position of the target 100; an electronic compass 150 for measuring at least an angle from the N pole of an X-axis or Y-axis constituting a piling plan; and a portable terminal 300 held by an operator of a base machine 10, etc. The portable terminal 300 comprises: a reception unit 320 for receiving measurement data transmitted from the measuring instrument 200 and the electronic compass 150; and a calculation unit 330 for reading the measurement data on the position of the target 100 and angle data from the reception unit 320 to calculate a pile core position of the steel pipe pile.SELECTED DRAWING: Figure 1
【課題】複雑な治具を有することなく、地盤の近傍において鋼管杭の杭芯位置を精度よく特定しながら鋼管杭の施工管理を行うことのできる、杭の施工管理方法、杭の施工管理システム、及び杭の施工管理システムを構成する携帯端末を提供すること。【解決手段】杭の施工管理システム500であり、振れ止め部材50の上、もしくは鋼管杭Pの周囲の地盤の上に固定されているターゲット100、ターゲット100の位置を計測する計測器200、杭伏図を構成するX軸もしくはY軸のN極からの角度を少なくとも計測する電子コンパス150、ベースマシン10のオペレータ等の有する携帯端末300を有し、携帯端末300は、計測器200と電子コンパス150から送信される計測データを受信する受信部320と、受信部320からターゲット100の位置と角度データに関する計測データを読み出し、鋼管杭の杭芯位置を演算する演算部330とを備える。【選択図】図1
PILE CONSTRUCTION MANAGEMENT METHOD, PILE CONSTRUCTION MANAGEMENT SYSTEM, AND PORTABLE TERMINAL CONSTITUTING PILE CONSTRUCTION MANAGEMENT SYSTEM
To provide a pile construction management method, a pile construction management system, and a portable terminal constituting the pile construction management system, capable of performing construction management on a steel pipe pile while accurately identifying a pile core position of the steel pipe pile in the vicinity of the ground without including any complicated jigs.SOLUTION: A pile construction management system 500 includes: a target 100 fixed on a bracing member 50 or the ground around a steel pipe pile P; a measuring instrument 200 for measuring a position of the target 100; an electronic compass 150 for measuring at least an angle from the N pole of an X-axis or Y-axis constituting a piling plan; and a portable terminal 300 held by an operator of a base machine 10, etc. The portable terminal 300 comprises: a reception unit 320 for receiving measurement data transmitted from the measuring instrument 200 and the electronic compass 150; and a calculation unit 330 for reading the measurement data on the position of the target 100 and angle data from the reception unit 320 to calculate a pile core position of the steel pipe pile.SELECTED DRAWING: Figure 1
【課題】複雑な治具を有することなく、地盤の近傍において鋼管杭の杭芯位置を精度よく特定しながら鋼管杭の施工管理を行うことのできる、杭の施工管理方法、杭の施工管理システム、及び杭の施工管理システムを構成する携帯端末を提供すること。【解決手段】杭の施工管理システム500であり、振れ止め部材50の上、もしくは鋼管杭Pの周囲の地盤の上に固定されているターゲット100、ターゲット100の位置を計測する計測器200、杭伏図を構成するX軸もしくはY軸のN極からの角度を少なくとも計測する電子コンパス150、ベースマシン10のオペレータ等の有する携帯端末300を有し、携帯端末300は、計測器200と電子コンパス150から送信される計測データを受信する受信部320と、受信部320からターゲット100の位置と角度データに関する計測データを読み出し、鋼管杭の杭芯位置を演算する演算部330とを備える。【選択図】図1
PILE CONSTRUCTION MANAGEMENT METHOD, PILE CONSTRUCTION MANAGEMENT SYSTEM, AND PORTABLE TERMINAL CONSTITUTING PILE CONSTRUCTION MANAGEMENT SYSTEM
杭の施工管理方法、杭の施工管理システム、及び杭の施工管理システムを構成する携帯端末
NAGAHAMA ATSUKO (Autor:in) / TAKAHASHI SHUICHI (Autor:in)
01.10.2020
Patent
Elektronische Ressource
Japanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Europäisches Patentamt | 2020
|Europäisches Patentamt | 2020
|PILE CONSTRUCTION METHOD AND PILE CONSTRUCTION MANAGEMENT SYSTEM
Europäisches Patentamt | 2019
|Europäisches Patentamt | 2020
|