Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
STEEL STRUCTURE PILE/COLUMN JOINT INTEGRATED COLUMN BASE STRUCTURE WITHOUT UNDERGROUND BEAM
To solve the problem, wherein conventionally, the construction of a building structure having an underground beam uses a large amount of reinforcing bars, formwork, and concrete, which causes the construction period and cost to become large.SOLUTION: One or more solid steel materials are attached to a top end of a steel pipe or concrete pile and then a square connecting steel pipe is welded onto it, and a pile head, a solid steel plate, and the lower part of a column are surrounded and solidified by reinforced concrete. A foundation body obtained in this way, or a concrete block, and a concrete floor slab are used together to bear the horizontal force during an earthquake and omit underground beams, leading to reduction in the process, construction period, cost, manpower, and steel frame construction.SELECTED DRAWING: Figure 11
【課題】従来、地中梁を有する建築構造体の建設は、鉄筋・型枠・コンクリートを多量に使い、その為に工期とコストが多大になるという問題がある。【解決手段】本発明は、鋼管又はコンクリート杭の上部の先に1つ又は複数枚の中実鋼材を取り付けてから、角形の接続鋼管をその上に溶接で取付け、且つ、杭頭・中実鋼板・柱下部を鉄筋コンクリートで囲い固めた基礎体・コンクリートブロック・コンクリート床スラブを併用して地震時の水平力を負担して地中梁を省略すれば、工程・工期・コスト・人手・鉄骨建て方の縮減が可能になる。【選択図】図11
STEEL STRUCTURE PILE/COLUMN JOINT INTEGRATED COLUMN BASE STRUCTURE WITHOUT UNDERGROUND BEAM
To solve the problem, wherein conventionally, the construction of a building structure having an underground beam uses a large amount of reinforcing bars, formwork, and concrete, which causes the construction period and cost to become large.SOLUTION: One or more solid steel materials are attached to a top end of a steel pipe or concrete pile and then a square connecting steel pipe is welded onto it, and a pile head, a solid steel plate, and the lower part of a column are surrounded and solidified by reinforced concrete. A foundation body obtained in this way, or a concrete block, and a concrete floor slab are used together to bear the horizontal force during an earthquake and omit underground beams, leading to reduction in the process, construction period, cost, manpower, and steel frame construction.SELECTED DRAWING: Figure 11
【課題】従来、地中梁を有する建築構造体の建設は、鉄筋・型枠・コンクリートを多量に使い、その為に工期とコストが多大になるという問題がある。【解決手段】本発明は、鋼管又はコンクリート杭の上部の先に1つ又は複数枚の中実鋼材を取り付けてから、角形の接続鋼管をその上に溶接で取付け、且つ、杭頭・中実鋼板・柱下部を鉄筋コンクリートで囲い固めた基礎体・コンクリートブロック・コンクリート床スラブを併用して地震時の水平力を負担して地中梁を省略すれば、工程・工期・コスト・人手・鉄骨建て方の縮減が可能になる。【選択図】図11
STEEL STRUCTURE PILE/COLUMN JOINT INTEGRATED COLUMN BASE STRUCTURE WITHOUT UNDERGROUND BEAM
鉄骨構造物地中梁無しの杭・柱接合部一体化柱脚構造
OTANI TOMONORI (Autor:in) / UCHIDA MASAKATSU (Autor:in)
01.03.2021
Patent
Elektronische Ressource
Japanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
STEEL STRUCTURE CONCRETE PILE, COLUMN, UNDERGROUND BEAM JOINT INTEGRATED COLUMN BASE STRUCTURE
Europäisches Patentamt | 2019
|PILE COLUMN JOINT STRUCTURE, AND CONSTRUCTION METHOD OF PILE COLUMN JOINT STRUCTURE
Europäisches Patentamt | 2020
|REINFORCED CONCRETE COLUMN/STEEL COLUMN/STEEL BEAM JOINT STRUCTURE
Europäisches Patentamt | 2016
|