To provide a viaduct construction method capable of shortening a construction period and reducing the area of a construction site even when there is a limit on an installation object.SOLUTION: A viaduct construction method applied to the construction of a viaduct, comprises the steps of: installing a plurality of frames 22 on a pair of bridge girders 20 supported by a plurality of bridge piers 10 and facing each other along the bridge axial direction of the viaduct; installing a plurality of transverse beams 40 on the tops of the plurality of frames so as to bridge the pair of bridge girders; installing a pair of rail beams 50 facing each other along the bridge axial direction of the viaduct on the plurality of transverse beams; installing a pair of rails R on the pair of rail beams, and placing a movable crane device 60 on the pair of rails.SELECTED DRAWING: Figure 3
【課題】設置対象に制約がある場合でも工期を短縮すると共に、建設用地を縮小できる高架橋構築工法を提供する。【解決手段】高架橋の構築に適用される高架橋構築工法であって、複数の橋脚10に支持されると共に、高架橋の橋軸方向に沿って対向する一対の橋桁上20に複数の架台22を設置する工程と、一対の橋桁を架橋するように複数の架台の上部に複数の横断梁40を設置する工程と、複数の横断梁上に高架橋の橋軸方向に沿って対向した一対のレール梁50を設置する工程と、一対のレール梁上に一対のレールRを設置する工程と、一対のレールに移動自在なクレーン装置60を載置する工程と、を備えることを特徴とする、高架橋構築工法。【選択図】図3
VIADUCT CONSTRUCTION METHOD AND VIADUCT CONSTRUCTION DEVICE
To provide a viaduct construction method capable of shortening a construction period and reducing the area of a construction site even when there is a limit on an installation object.SOLUTION: A viaduct construction method applied to the construction of a viaduct, comprises the steps of: installing a plurality of frames 22 on a pair of bridge girders 20 supported by a plurality of bridge piers 10 and facing each other along the bridge axial direction of the viaduct; installing a plurality of transverse beams 40 on the tops of the plurality of frames so as to bridge the pair of bridge girders; installing a pair of rail beams 50 facing each other along the bridge axial direction of the viaduct on the plurality of transverse beams; installing a pair of rails R on the pair of rail beams, and placing a movable crane device 60 on the pair of rails.SELECTED DRAWING: Figure 3
【課題】設置対象に制約がある場合でも工期を短縮すると共に、建設用地を縮小できる高架橋構築工法を提供する。【解決手段】高架橋の構築に適用される高架橋構築工法であって、複数の橋脚10に支持されると共に、高架橋の橋軸方向に沿って対向する一対の橋桁上20に複数の架台22を設置する工程と、一対の橋桁を架橋するように複数の架台の上部に複数の横断梁40を設置する工程と、複数の横断梁上に高架橋の橋軸方向に沿って対向した一対のレール梁50を設置する工程と、一対のレール梁上に一対のレールRを設置する工程と、一対のレールに移動自在なクレーン装置60を載置する工程と、を備えることを特徴とする、高架橋構築工法。【選択図】図3
VIADUCT CONSTRUCTION METHOD AND VIADUCT CONSTRUCTION DEVICE
高架橋構築工法及び高架橋構築装置
YOSHITAKE KENJI (Autor:in) / FUNAOKA MOTOI (Autor:in)