CONSTRUCTION METHOD OF RUBBLE CONCRETE
To provide a construction method of rubble concrete capable of constructing rubble concrete without requiring installation of wales and short struts inside a planarly extending earth retaining wall.SOLUTION: A construction method of rubble concrete includes: an A step of constructing an earth retaining wall 10 on a ground G and excavating to a position becoming a bottom face of rubble concrete to be constructed to construct a first leveling work surface S1 inside the same; a B step of constructing center rubble concrete 20 on the same; a C step of intermittently excavating the ground between the lateral side of the center rubble concrete 20 and the earth retaining wall 10 in plan view to construct a plurality of second leveling work surfaces S2; and a D step of constructing strut rubble concrete 30 on the same. By sequentially repeating the C step and the D step, a plurality of strut rubble concretes 30, 40 connecting the lateral side of the center rubble concrete 20 and the earth retaining wall 10 are constructed, and a rubble concrete unit 60 comprising these is constructed.SELECTED DRAWING: Figure 2A
【課題】平面的に広がりのある山留壁の内側に、腹起しと切梁の設置を不要にしてラップルコンクリートを施工できる、ラップルコンクリートの施工方法を提供すること。【解決手段】ラップルコンクリートの施工方法は、地盤Gに山留壁10を施工し、その内側に後施工されるラップルコンクリートの底面となる位置まで掘削して第1床付け面S1を施工するA工程、その上に中央ラップルコンクリート20を施工するB工程、中央ラップルコンクリート20の側方と山留壁10の間の地盤を平面視において間欠的に掘削して、複数の第2床付け面S2を施工するC工程、それらの上にストラットラップルコンクリート30を施工するD工程を有し、C工程とD工程を順次繰り返すことにより、中央ラップルコンクリート20の側方と山留壁10を繋ぐ複数のストラットラップルコンクリート30,40が施工され、これらからなるラップルコンクリートユニット60を施工する。【選択図】図2A
CONSTRUCTION METHOD OF RUBBLE CONCRETE
To provide a construction method of rubble concrete capable of constructing rubble concrete without requiring installation of wales and short struts inside a planarly extending earth retaining wall.SOLUTION: A construction method of rubble concrete includes: an A step of constructing an earth retaining wall 10 on a ground G and excavating to a position becoming a bottom face of rubble concrete to be constructed to construct a first leveling work surface S1 inside the same; a B step of constructing center rubble concrete 20 on the same; a C step of intermittently excavating the ground between the lateral side of the center rubble concrete 20 and the earth retaining wall 10 in plan view to construct a plurality of second leveling work surfaces S2; and a D step of constructing strut rubble concrete 30 on the same. By sequentially repeating the C step and the D step, a plurality of strut rubble concretes 30, 40 connecting the lateral side of the center rubble concrete 20 and the earth retaining wall 10 are constructed, and a rubble concrete unit 60 comprising these is constructed.SELECTED DRAWING: Figure 2A
【課題】平面的に広がりのある山留壁の内側に、腹起しと切梁の設置を不要にしてラップルコンクリートを施工できる、ラップルコンクリートの施工方法を提供すること。【解決手段】ラップルコンクリートの施工方法は、地盤Gに山留壁10を施工し、その内側に後施工されるラップルコンクリートの底面となる位置まで掘削して第1床付け面S1を施工するA工程、その上に中央ラップルコンクリート20を施工するB工程、中央ラップルコンクリート20の側方と山留壁10の間の地盤を平面視において間欠的に掘削して、複数の第2床付け面S2を施工するC工程、それらの上にストラットラップルコンクリート30を施工するD工程を有し、C工程とD工程を順次繰り返すことにより、中央ラップルコンクリート20の側方と山留壁10を繋ぐ複数のストラットラップルコンクリート30,40が施工され、これらからなるラップルコンクリートユニット60を施工する。【選択図】図2A
CONSTRUCTION METHOD OF RUBBLE CONCRETE
ラップルコンクリートの施工方法
TOSAUCHI YUSUKE (Autor:in) / MISHIMA SHINYA (Autor:in) / KAMOSHITA YOSHINORI (Autor:in) / USAGAWA AKANE (Autor:in) / MIYAZAWA SHO (Autor:in)
28.03.2023
Patent
Elektronische Ressource
Japanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
RUBBLE BASE CONSTRUCTION SYSTEM AND RUBBLE BASE CONSTRUCTION METHOD
Europäisches Patentamt | 2023
|RUBBLE MOUND CONSTRUCTION SYSTEM AND RUBBLE MOUND CONSTRUCTION METHOD
Europäisches Patentamt | 2021
|Europäisches Patentamt | 2023
|Springer Verlag | 2022
|Concrete from limestone rubble
Engineering Index Backfile | 1912
|