METHOD FOR REDUCING FACILITY IN TUNNEL CONSTRUCTION BY USING DRILLING HOLE
The present invention relates to a tunnel construction method. The tunnel construction method comprises: a first facility connection step of installing a facility to supply water, draining water, and supplying power on one end of both tunnel mouths wherein a tunnel is excavated; a first excavation step of excavating a first section, which is a section from the one end, where the facility is installed in the first facility connection step to a penetration unit which is a point in between one end of the tunnel and an other end of the tunnel; a hole drilling step of drilling a through hole penetrating a second section which is a section from the penetration unit of the tunnel to the other end of the tunnel on one side of a surface into which the tunnel is excavated; a second facility connection step of connecting a facility line connected to the facility installed in the first facility connection step to the other end of the tunnel through the through hole formed in the hole drilling step; and a second excavation step of using the facility line connected in the second facility connection step to excavate the second section of the tunnel to penetrate the tunnel.
본 발명은 터널 시공방법에 관한 것으로 터널이 굴착되는 양 갱구부 중 일단부에 급수, 배수 및 전력공급을 위한 설비가 설치되는 제1 설비연결 단계; 상기 제1 설비연결 단계에서 상기 설비가 설치된 상기 일단부로부터 상기 터널의 일단부 및 타단부 사이의 지점인 관통부까지의 구간인, 제1 구간을 굴착하는 제1 굴착 단계; 상기 터널이 굴착되는 면의 일측에, 상기 터널의 상기 관통부로부터 상기 터널의 상기 타단부까지의 구간인, 제2 구간을 관통하는 관통홀을 천공하는 천공 단계; 상기 제1 설비연결 단계에서 설치된 상기 설비와 연결되는 설비라인을, 상기 천공 단계에서 형성된 상기 관통홀을 통해 상기 터널의 타단부까지 연결하는 제2 설비연결 단계; 및 상기 제2 설비연결 단계에서 연결된 상기 설비라인을 이용하여 상기 터널의 상기 제2 구간을 굴착하여 상기 터널을 관통시키는 제2 굴착 단계;를 포함한다.
METHOD FOR REDUCING FACILITY IN TUNNEL CONSTRUCTION BY USING DRILLING HOLE
The present invention relates to a tunnel construction method. The tunnel construction method comprises: a first facility connection step of installing a facility to supply water, draining water, and supplying power on one end of both tunnel mouths wherein a tunnel is excavated; a first excavation step of excavating a first section, which is a section from the one end, where the facility is installed in the first facility connection step to a penetration unit which is a point in between one end of the tunnel and an other end of the tunnel; a hole drilling step of drilling a through hole penetrating a second section which is a section from the penetration unit of the tunnel to the other end of the tunnel on one side of a surface into which the tunnel is excavated; a second facility connection step of connecting a facility line connected to the facility installed in the first facility connection step to the other end of the tunnel through the through hole formed in the hole drilling step; and a second excavation step of using the facility line connected in the second facility connection step to excavate the second section of the tunnel to penetrate the tunnel.
본 발명은 터널 시공방법에 관한 것으로 터널이 굴착되는 양 갱구부 중 일단부에 급수, 배수 및 전력공급을 위한 설비가 설치되는 제1 설비연결 단계; 상기 제1 설비연결 단계에서 상기 설비가 설치된 상기 일단부로부터 상기 터널의 일단부 및 타단부 사이의 지점인 관통부까지의 구간인, 제1 구간을 굴착하는 제1 굴착 단계; 상기 터널이 굴착되는 면의 일측에, 상기 터널의 상기 관통부로부터 상기 터널의 상기 타단부까지의 구간인, 제2 구간을 관통하는 관통홀을 천공하는 천공 단계; 상기 제1 설비연결 단계에서 설치된 상기 설비와 연결되는 설비라인을, 상기 천공 단계에서 형성된 상기 관통홀을 통해 상기 터널의 타단부까지 연결하는 제2 설비연결 단계; 및 상기 제2 설비연결 단계에서 연결된 상기 설비라인을 이용하여 상기 터널의 상기 제2 구간을 굴착하여 상기 터널을 관통시키는 제2 굴착 단계;를 포함한다.
METHOD FOR REDUCING FACILITY IN TUNNEL CONSTRUCTION BY USING DRILLING HOLE
천공홀을 이용한 터널 설비 축소방법
PARK JONG HO (Autor:in) / PARK SANG HYUN (Autor:in) / KWON GI SEONG (Autor:in) / KIM HYO SEONG (Autor:in)
05.02.2016
Patent
Elektronische Ressource
Koreanisch
Hole body pretreatment method for reducing drilling resistance
Europäisches Patentamt | 2022
|Hole drilling method and casing for hole drilling only
Europäisches Patentamt | 2024
|PILE HOLE DRILLING DEVICE AND PILE CONSTRUCTION MANAGEMENT METHOD
Europäisches Patentamt | 2017
|