MULTI PILE CONSTRUCTION METHOD FOR STRENGTHENING WEAK SOIL
The present invention relates to a multi-pile construction method for reinforcing soft ground wherein a construction period can be reduced as a punching process for forming an excavation hole and an insertion process for inserting a main pile are performed at the same time and high quality of the construction can be obtained by injecting a grout material at high density. The multi-pile construction method for reinforcing soft ground comprises the following steps: locating a ring bit and a pilot bit on a lower end portion of the main pile by installing a punching device, which comprises a drill rod and a pilot bit joined to a lower end portion of the drill rod, on the main pile which comprises a steel pipe, having a grout material discharge hole, and the ring bit installed to be able to rotate on a lower end portion of the steel pipe; performing punching of the excavation hole and insertion of the main pile at the same time by rotating the ring bit and the pilot bit with rotation of the drill rod and pressing and inserting the ring bit and the pilot bit into the soft ground at the same time in a state after the punching device is installed on the main pile; separating and removing the punching device from the main pile after the main pile is inserted in a certain depth into the soft ground in a certain depth; injecting the grout material in the excavation hole; and curing the grout material.
본 발명은 연약지반 강화를 위한 다중말뚝 시공방법에 관한 것으로, 굴착공을 형성하는 천공작업과 주말뚝을 관입하는 관입작업이 동시에 진행되어 공사기간을 단축할 수 있고 그라우트재를 고밀도로 주입하여 높은 공사품질을 얻을 수 있도록 한 것이다. 이러한 본 발명은, 그라우트재 배출공이 형성된 강관과 상기 강관의 하단에 회전 가능하게 설치된 링비트(ring bit)로 이루어진 주말뚝에 대하여 드릴로드(drill rod)와 상기 드릴로드 하단에 결합된 파일롯비트(pilot bit)로 이루어진 천공장치를 장착하여 상기 링비트와 함께 상기 파일롯비트를 상기 주말뚝 하단에 위치시키는 단계와; 상기 주말뚝에 상기 천공장치가 장착된 상태에서 상기 드릴로드의 회전을 통해 상기 링비트와 파일롯비트를 회전시키면서 연약지반에 압입시킴으로써 굴착공의 천공과 주말뚝의 관입을 동시에 실시하는 단계와; 상기 주말뚝이 연약지반에 일정 깊이 관입되면 상기 천공장치를 상기 주말뚝으로부터 분리하여 제거하는 단계와; 상기 굴착공에 그라우트재를 주입하는 단계와; 상기 그라우트재를 경화시키는 단계를 포함하여 이루어진다.
MULTI PILE CONSTRUCTION METHOD FOR STRENGTHENING WEAK SOIL
The present invention relates to a multi-pile construction method for reinforcing soft ground wherein a construction period can be reduced as a punching process for forming an excavation hole and an insertion process for inserting a main pile are performed at the same time and high quality of the construction can be obtained by injecting a grout material at high density. The multi-pile construction method for reinforcing soft ground comprises the following steps: locating a ring bit and a pilot bit on a lower end portion of the main pile by installing a punching device, which comprises a drill rod and a pilot bit joined to a lower end portion of the drill rod, on the main pile which comprises a steel pipe, having a grout material discharge hole, and the ring bit installed to be able to rotate on a lower end portion of the steel pipe; performing punching of the excavation hole and insertion of the main pile at the same time by rotating the ring bit and the pilot bit with rotation of the drill rod and pressing and inserting the ring bit and the pilot bit into the soft ground at the same time in a state after the punching device is installed on the main pile; separating and removing the punching device from the main pile after the main pile is inserted in a certain depth into the soft ground in a certain depth; injecting the grout material in the excavation hole; and curing the grout material.
본 발명은 연약지반 강화를 위한 다중말뚝 시공방법에 관한 것으로, 굴착공을 형성하는 천공작업과 주말뚝을 관입하는 관입작업이 동시에 진행되어 공사기간을 단축할 수 있고 그라우트재를 고밀도로 주입하여 높은 공사품질을 얻을 수 있도록 한 것이다. 이러한 본 발명은, 그라우트재 배출공이 형성된 강관과 상기 강관의 하단에 회전 가능하게 설치된 링비트(ring bit)로 이루어진 주말뚝에 대하여 드릴로드(drill rod)와 상기 드릴로드 하단에 결합된 파일롯비트(pilot bit)로 이루어진 천공장치를 장착하여 상기 링비트와 함께 상기 파일롯비트를 상기 주말뚝 하단에 위치시키는 단계와; 상기 주말뚝에 상기 천공장치가 장착된 상태에서 상기 드릴로드의 회전을 통해 상기 링비트와 파일롯비트를 회전시키면서 연약지반에 압입시킴으로써 굴착공의 천공과 주말뚝의 관입을 동시에 실시하는 단계와; 상기 주말뚝이 연약지반에 일정 깊이 관입되면 상기 천공장치를 상기 주말뚝으로부터 분리하여 제거하는 단계와; 상기 굴착공에 그라우트재를 주입하는 단계와; 상기 그라우트재를 경화시키는 단계를 포함하여 이루어진다.
MULTI PILE CONSTRUCTION METHOD FOR STRENGTHENING WEAK SOIL
연약지반 강화를 위한 다중말뚝 시공방법
JANG GI SU (Autor:in)
23.01.2017
Patent
Elektronische Ressource
Koreanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Europäisches Patentamt | 2020
|STRENGTHENING FIXTURE, STRENGTHENING METHOD AND PILE PENETRATION METHOD