Retaining Wall Using Pile With Center Hole And Construction Method Thereof
The present invention relates to a retaining wall construction method using a hollow pile reinforced with steel and concrete, including installing a guide frame after ground excavation or trimming; inserting hollow piles while or after forming perforation holes in the ground by means of the guide frame; inserting reinforcing materials into the piles; pouring concrete into the piles; excavating the front portions of the piles; installing connectors on the front portions of the piles; installing impermeable separation walls in the connectors; horizontally installing guide bars in the connectors; vertically installing a perforated pipe on the rear surface of the separation wall; filling at least one of sand, gravel, and rubble in the rear surface of the separation wall; installing cap concrete on top of the piles; placing foundation concrete under the piles; installing a support on the guide bar; and installing a finishing wall on the support. With the present invention, a retaining wall as high as 4 to 6 meters or more can be highly stably built. In addition, a retaining wall with a height of 4 to 6 meters or less can be economically built by means of reinforcing net or H beam insertion into a thin corrugated steel pipe or corrugated plastic pipe pile and high strength concrete placement and reinforcement inside.
본 발명은 지반을 굴착하거나 정리한 후 가이드프레임을 설치하는 단계; 상기 가이드프레임을 이용하여 상기 지반에 천공구들을 형성하면서, 또는 천공구들을 형성한 후 중공형의 말뚝들을 삽입하는 단계; 상기 말뚝들의 내부에 보강재들을 삽입하는 단계; 상기 말뚝들의 내부에 콘크리트를 타설하는 단계; 상기 말뚝들의 전면부를 굴착하는 단계; 상기 말뚝들의 전면부에 연결재들을 설치하는 단계; 상기 연결재들에 불투수성 분리벽체들을 설치하는 단계; 상기 연결재들에 가이드바들을 수평방향으로 설치하는 단계; 상기 분리벽체의 배면에 유공관을 연직방향으로 설치하는 단계; 상기 분리벽체의 배면에 모래, 자갈, 잡석 중 하나 이상을 채우는 단계; 상기 말뚝들의 상부에 캡콘크리트를 설치하는 단계; 상기 말뚝들의 하부에 기초콘크리트를 타설하는 단계; 상기 가이드바에 받침을 설치하는 단계; 상기 받침에 마감벽을 설치하는 단계;를 포함하는 강재와 콘크리트로 보강된 중공형 말뚝을 활용한 용벽 시공방법에 관한 것으로서, 4~6m 이상으로 높이가 높은 옹벽을 안정성이 우수하게 시공할 수 있고, 높이가 4~6m 이하인 옹벽의 경우 두께가 얇은 파형강관이나 파형플라스틱관 막뚝 내부에 철근망이나 H빔을 삽입하고 내부에 고강도 콘크리트를 타설하여 보강함으로써, 경제적으로 옹벽을 시공할 수 있는 효과를 가질 수 있다.
Retaining Wall Using Pile With Center Hole And Construction Method Thereof
The present invention relates to a retaining wall construction method using a hollow pile reinforced with steel and concrete, including installing a guide frame after ground excavation or trimming; inserting hollow piles while or after forming perforation holes in the ground by means of the guide frame; inserting reinforcing materials into the piles; pouring concrete into the piles; excavating the front portions of the piles; installing connectors on the front portions of the piles; installing impermeable separation walls in the connectors; horizontally installing guide bars in the connectors; vertically installing a perforated pipe on the rear surface of the separation wall; filling at least one of sand, gravel, and rubble in the rear surface of the separation wall; installing cap concrete on top of the piles; placing foundation concrete under the piles; installing a support on the guide bar; and installing a finishing wall on the support. With the present invention, a retaining wall as high as 4 to 6 meters or more can be highly stably built. In addition, a retaining wall with a height of 4 to 6 meters or less can be economically built by means of reinforcing net or H beam insertion into a thin corrugated steel pipe or corrugated plastic pipe pile and high strength concrete placement and reinforcement inside.
본 발명은 지반을 굴착하거나 정리한 후 가이드프레임을 설치하는 단계; 상기 가이드프레임을 이용하여 상기 지반에 천공구들을 형성하면서, 또는 천공구들을 형성한 후 중공형의 말뚝들을 삽입하는 단계; 상기 말뚝들의 내부에 보강재들을 삽입하는 단계; 상기 말뚝들의 내부에 콘크리트를 타설하는 단계; 상기 말뚝들의 전면부를 굴착하는 단계; 상기 말뚝들의 전면부에 연결재들을 설치하는 단계; 상기 연결재들에 불투수성 분리벽체들을 설치하는 단계; 상기 연결재들에 가이드바들을 수평방향으로 설치하는 단계; 상기 분리벽체의 배면에 유공관을 연직방향으로 설치하는 단계; 상기 분리벽체의 배면에 모래, 자갈, 잡석 중 하나 이상을 채우는 단계; 상기 말뚝들의 상부에 캡콘크리트를 설치하는 단계; 상기 말뚝들의 하부에 기초콘크리트를 타설하는 단계; 상기 가이드바에 받침을 설치하는 단계; 상기 받침에 마감벽을 설치하는 단계;를 포함하는 강재와 콘크리트로 보강된 중공형 말뚝을 활용한 용벽 시공방법에 관한 것으로서, 4~6m 이상으로 높이가 높은 옹벽을 안정성이 우수하게 시공할 수 있고, 높이가 4~6m 이하인 옹벽의 경우 두께가 얇은 파형강관이나 파형플라스틱관 막뚝 내부에 철근망이나 H빔을 삽입하고 내부에 고강도 콘크리트를 타설하여 보강함으로써, 경제적으로 옹벽을 시공할 수 있는 효과를 가질 수 있다.
Retaining Wall Using Pile With Center Hole And Construction Method Thereof
강재와 콘크리트로 보강된 중공형 말뚝을 활용한 옹벽 및 그 시공방법
ROH KYUNG BEOM (Autor:in) / ROH U HYEON (Autor:in) / NO SIL GEUN (Autor:in) / NO YOK GEUN (Autor:in) / PARK CHI WOONG (Autor:in) / WOO SANG BAIK (Autor:in)
24.08.2018
Patent
Elektronische Ressource
Koreanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Pile hole retaining wall construction method suitable for bridge road construction
Europäisches Patentamt | 2023
|Construction method for retaining wall of manual hole digging pile
Europäisches Patentamt | 2024
|Construction method for retaining wall of manual hole digging pile
Europäisches Patentamt | 2024
|PILE MODULE RETAINING WALL AND CONSTRUCTION METHOD THEREOF
Europäisches Patentamt | 2016
|Retaining Wall Structure with Muck Pile and Retaining Wall Construction Method
Europäisches Patentamt | 2020
|