The present invention relates to a method of constructing a sheet pile using a special casing and, more specifically, to a sheet pile construction method, capable of driving the sheet pile without a separate sand filling process after drilling by engaging a connection part guide of the special casing with a connection part of a previously installed sheet pile to perform press-fitting while using the engaged portion as a guide. The present invention makes it possible to increase the drilling force by forming an auger integrated with a rack gear, makes it easy to manage drilling verticality by engaging the connection part guide of the special casing with the pre-installed sheet pile to perform drilling while using the engaged portion as a guide, prevents damage to the pre-installed sheet pile and improves a drilling speed by full face cutting in all strata (including sandstone and bedrock layer) through an increase in the diameter of the tip of a hammer bit to reduce the time required for drilling.
본 발명은 특수케이싱을 이용한 시트파일 시공방법에 관한 것으로 구체적으로는 특수케이싱의 연결부가이드가 기설치된 시트파일의 연결부와 맞물려 이를 가이드삼아 압입하여 천공항 후 별도의 모래채움 공정 없이 시트파일을 항타할 수 있는 시트파일 시공방법에 관한 것이다. 본 발명의 렉기어와 일체형 오거를 형성시킴으로서 천공력을 증가시킬 수 있으며, 특수케이싱의 연결부가이드를 기 설치된 시트파일과 맞물려서 가이드삼아 천공되도록 함으로서 천공 수직도 관리가 용이하며 기설치된 시트파일 손상을 방지하는 효과가 있으며, 햄머비트의 선단확경을 통해 모든 지층(사석, 암반층 포함)에서 전단면 굴착으로 천공속도가 향상되어 천공 소요시간을 단축하는 효과가 있다.
Construction Method of Sheet Pile Using Special Casing
The present invention relates to a method of constructing a sheet pile using a special casing and, more specifically, to a sheet pile construction method, capable of driving the sheet pile without a separate sand filling process after drilling by engaging a connection part guide of the special casing with a connection part of a previously installed sheet pile to perform press-fitting while using the engaged portion as a guide. The present invention makes it possible to increase the drilling force by forming an auger integrated with a rack gear, makes it easy to manage drilling verticality by engaging the connection part guide of the special casing with the pre-installed sheet pile to perform drilling while using the engaged portion as a guide, prevents damage to the pre-installed sheet pile and improves a drilling speed by full face cutting in all strata (including sandstone and bedrock layer) through an increase in the diameter of the tip of a hammer bit to reduce the time required for drilling.
본 발명은 특수케이싱을 이용한 시트파일 시공방법에 관한 것으로 구체적으로는 특수케이싱의 연결부가이드가 기설치된 시트파일의 연결부와 맞물려 이를 가이드삼아 압입하여 천공항 후 별도의 모래채움 공정 없이 시트파일을 항타할 수 있는 시트파일 시공방법에 관한 것이다. 본 발명의 렉기어와 일체형 오거를 형성시킴으로서 천공력을 증가시킬 수 있으며, 특수케이싱의 연결부가이드를 기 설치된 시트파일과 맞물려서 가이드삼아 천공되도록 함으로서 천공 수직도 관리가 용이하며 기설치된 시트파일 손상을 방지하는 효과가 있으며, 햄머비트의 선단확경을 통해 모든 지층(사석, 암반층 포함)에서 전단면 굴착으로 천공속도가 향상되어 천공 소요시간을 단축하는 효과가 있다.
Construction Method of Sheet Pile Using Special Casing
특수케이싱을 이용한 사석 암반층 시트파일 시공방법