Pillar Grouting Method in Underground Cavern
The present invention relates to a pillar grouting method in an underground cavern. The pillar grouting method in an underground cavern comprises: a step of boring a hole for filling aggregate; a step of maintaining the shape of the hole by installing a casing in an earth layer of the hole; a step of inserting an aggregate filling pipe into the casing; a step of filling the cavity with aggregate; a step of drawing out and removing the aggregate filling pipe from the casing; a step of forming a borehole in the bedrock in the cavity in a certain depth; a step of installing a grout injection pipe; a step of inserting a hose into the grout injection pipe; a step of forming a pillar by injecting a grout material using pressure and injecting pressure to a non-filled part in the top of the cavity and an opening part and a relaxed zone of the ground on the top of the cavity; and a step of completing pillar grouting construction, thereby filling most parts of the cavity with cost-efficient coarse aggregate or fine aggregate.
본 발명은 지하 공동의 필라 그라우팅 공법에 관한 것이다. 본 발명은, 확인된 공동 상부까지 골재충전용 홀을 천공하는 단계와; 상기 홀의 토층에 케이싱을 설치하여 상기 홀의 형상을 유지하는 단계와; 상기 케이싱 내부에 골재충전관을 삽입 설치하는 단계와; 상기 골재충전관을 통하여 공기나 물 압력을 가하는 방법과 자유낙하방법 중 선택된 어느 하나의 방법으로 상기 공동내에 골재를 충전하는 단계와;상기 케이싱 내의 골재충전관을 인발하여 제거하는 단계와; 천공기를 사용하여 기 형성된 골재충전홀과 상기 공동내 충전된 골재 충전층을 관통하여 상기 공동의 기반암 바닥에 일정한 깊이로 천공홀을 형성하는 단계와; 그라우트 주입관의 상단부가 상기 홀의 지표면 영역에 위치하고 하단부는 공동 내의 하부 기반암 바닥에 형성된 상기 천공홀에 삽입되어 유동됨이 없도록 그라우트 주입관을 설치하는 단계와; 상기 그라우트 주입관 내에 하부 영역까지 패커가 설치된 호스를 삽입하는 단계와; 상기 그라우트 주입관 내에 위치하며 상기 패커가 설치된 호스를 단계별 일정한 심도로 인발하면서 상기 패커를 통해 그라우트재를 압력주입하여 필라(Pillar)를 형성시키고, 공동상부의 미충전부와 공동상부지반의 공극부 및 이완대를 압력주입하는 단계와; 상기 천공으로부터 상기 케이싱을 인발하여 지하 공동의 필라 그라우팅 시공을 완료하는 단계로 이루어진 것을 특징으로 한다. 이에 의해, 공동의 충전재로 가격이 저렴하여 경제적인 조골재 또는 세골재를 중력투입하여 공동의 대부분을 충전할 수 있는 이점이 있으며, 조골재 내 공극부와 상부 미충전 부분에 밀크를 압력주입하여 밀실한 충전이 가능토록 공동 충전기능뿐만 아니라 공동 상부의 하중을 지지할 수 있는 필라(Pillar)의 역할을 할 수 있는 이점과, 강관으로 형성된 그라우트 주입관이 구조적 보강재로서의 역할을 하여 상부하중을 공동 내의 하부 기반암에 전달하는 기능을 하고, 충전구간에서 전단보강재로서의 역할을 하여 지진 등의 진동에 저항력이 높은 이점과, 그라우팅시 겔타임을 조절하여 기둥의 크기와 형태를 조절할 수 있는 이점과, 공동 상부 지반의 이완대에 밀실한 충전이 가능한 이점과 더불어 골재를 충전함에 따라 별도의 실링작업이 없다는 이점이 있다.
Pillar Grouting Method in Underground Cavern
The present invention relates to a pillar grouting method in an underground cavern. The pillar grouting method in an underground cavern comprises: a step of boring a hole for filling aggregate; a step of maintaining the shape of the hole by installing a casing in an earth layer of the hole; a step of inserting an aggregate filling pipe into the casing; a step of filling the cavity with aggregate; a step of drawing out and removing the aggregate filling pipe from the casing; a step of forming a borehole in the bedrock in the cavity in a certain depth; a step of installing a grout injection pipe; a step of inserting a hose into the grout injection pipe; a step of forming a pillar by injecting a grout material using pressure and injecting pressure to a non-filled part in the top of the cavity and an opening part and a relaxed zone of the ground on the top of the cavity; and a step of completing pillar grouting construction, thereby filling most parts of the cavity with cost-efficient coarse aggregate or fine aggregate.
본 발명은 지하 공동의 필라 그라우팅 공법에 관한 것이다. 본 발명은, 확인된 공동 상부까지 골재충전용 홀을 천공하는 단계와; 상기 홀의 토층에 케이싱을 설치하여 상기 홀의 형상을 유지하는 단계와; 상기 케이싱 내부에 골재충전관을 삽입 설치하는 단계와; 상기 골재충전관을 통하여 공기나 물 압력을 가하는 방법과 자유낙하방법 중 선택된 어느 하나의 방법으로 상기 공동내에 골재를 충전하는 단계와;상기 케이싱 내의 골재충전관을 인발하여 제거하는 단계와; 천공기를 사용하여 기 형성된 골재충전홀과 상기 공동내 충전된 골재 충전층을 관통하여 상기 공동의 기반암 바닥에 일정한 깊이로 천공홀을 형성하는 단계와; 그라우트 주입관의 상단부가 상기 홀의 지표면 영역에 위치하고 하단부는 공동 내의 하부 기반암 바닥에 형성된 상기 천공홀에 삽입되어 유동됨이 없도록 그라우트 주입관을 설치하는 단계와; 상기 그라우트 주입관 내에 하부 영역까지 패커가 설치된 호스를 삽입하는 단계와; 상기 그라우트 주입관 내에 위치하며 상기 패커가 설치된 호스를 단계별 일정한 심도로 인발하면서 상기 패커를 통해 그라우트재를 압력주입하여 필라(Pillar)를 형성시키고, 공동상부의 미충전부와 공동상부지반의 공극부 및 이완대를 압력주입하는 단계와; 상기 천공으로부터 상기 케이싱을 인발하여 지하 공동의 필라 그라우팅 시공을 완료하는 단계로 이루어진 것을 특징으로 한다. 이에 의해, 공동의 충전재로 가격이 저렴하여 경제적인 조골재 또는 세골재를 중력투입하여 공동의 대부분을 충전할 수 있는 이점이 있으며, 조골재 내 공극부와 상부 미충전 부분에 밀크를 압력주입하여 밀실한 충전이 가능토록 공동 충전기능뿐만 아니라 공동 상부의 하중을 지지할 수 있는 필라(Pillar)의 역할을 할 수 있는 이점과, 강관으로 형성된 그라우트 주입관이 구조적 보강재로서의 역할을 하여 상부하중을 공동 내의 하부 기반암에 전달하는 기능을 하고, 충전구간에서 전단보강재로서의 역할을 하여 지진 등의 진동에 저항력이 높은 이점과, 그라우팅시 겔타임을 조절하여 기둥의 크기와 형태를 조절할 수 있는 이점과, 공동 상부 지반의 이완대에 밀실한 충전이 가능한 이점과 더불어 골재를 충전함에 따라 별도의 실링작업이 없다는 이점이 있다.
Pillar Grouting Method in Underground Cavern
지하 공동의 필라 그라우팅 공법
PARK NAM SEO (Autor:in) / HA EUN YOUNG (Autor:in) / LEE SANG MOO (Autor:in)
24.11.2016
Patent
Elektronische Ressource
Koreanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Seepage prevention method for sealing large underground cavern by adopting advanced grouting
Europäisches Patentamt | 2021
|Pre-consolidation grouting system for top arch and side wall of large underground cavern
Europäisches Patentamt | 2023
|Underground cavern excavation : final report
TIBKAT | 1986
Grouting slurry and underground pipeline grouting method
Europäisches Patentamt | 2022
|