Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project
According to the present invention, in order to shorten a period for basement framework construction in a basement top-down method for construction, provided is a construction method wherein basement vertical members (core parts, pillars) are alternately constructed to a lower floor and then remaining vertical members are constructed at the same, thereby shortening a construction period. According to the present invention, the top-down construction method performing alternate connection includes: a first step of installing a retaining wall and constructing a basement pillar post, and then, excavating a bed for a first basement floor and constructing a first ground floor; a second step of first constructing a core part of the first basement floor to support a core part of the ground floor constructed upward while constructing a basement floor slab to a lower floor; a third step of constructing basement vertical members downward on an alternate basis floor by floor by using a bottom-up method; and a step of constructing the lowermost mat or foundation, and then, constructing basement vertical members for remaining floors at the same time or step by step by using the bottom-up method. Therefore, since a period for the construction of basement vertical members is shortened, subsequent ground framework and finishing construction can be started at an early stage, which can lead to a reduction in the entire construction period.
본 발명은 건설공사 지하층 역타공법 탑다운에서의 지하 골조공사 기간을 단축하기 위한 것으로, 지하 수직부재(코어부, 기둥)를 하나 걸러 번갈아 가면서 아래층으로 시공하며 이후에는 남은 수직부재를 동시에 시공하는 공사방법을 제공하여 공사기간을 단축할 수 있도록 한다. 본 발명에 따른 하나 걸러 번갈아 이어지는 역타공법의 공사방법은 흙막이를 설치하고 지하 기둥말뚝을 시공한 후, 지하 1층 터파기 및 지상 1층 바닥을 시공하는 제1단계 ; 지하층 슬라브를 아래층으로 시공하면서 상향 시공되는 지상층 코어부를 지지하기 위하여 지하 1개층 코어부를 먼저 시공하는 제2단계 ; 지하 수직부재를 하나 걸러 번갈아 가며 하향으로 순타로 1개층씩 시공하는 제3단계 ; 최하층 매트 또는 기초를 시공한 후, 하나걸러 남은 잔여층 지하 부직부재를 동시에 또는 단계별로 순타로 시공하는 단계 ; 로 이루어져 지하 수직부재 공사기간을 단축함으로써 이후의 지상 골조 및 마감공사를 조기에 착수할 수 있게 되어 전체 공사기간을 단축하는 것을 특징으로 한다.
Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project
According to the present invention, in order to shorten a period for basement framework construction in a basement top-down method for construction, provided is a construction method wherein basement vertical members (core parts, pillars) are alternately constructed to a lower floor and then remaining vertical members are constructed at the same, thereby shortening a construction period. According to the present invention, the top-down construction method performing alternate connection includes: a first step of installing a retaining wall and constructing a basement pillar post, and then, excavating a bed for a first basement floor and constructing a first ground floor; a second step of first constructing a core part of the first basement floor to support a core part of the ground floor constructed upward while constructing a basement floor slab to a lower floor; a third step of constructing basement vertical members downward on an alternate basis floor by floor by using a bottom-up method; and a step of constructing the lowermost mat or foundation, and then, constructing basement vertical members for remaining floors at the same time or step by step by using the bottom-up method. Therefore, since a period for the construction of basement vertical members is shortened, subsequent ground framework and finishing construction can be started at an early stage, which can lead to a reduction in the entire construction period.
본 발명은 건설공사 지하층 역타공법 탑다운에서의 지하 골조공사 기간을 단축하기 위한 것으로, 지하 수직부재(코어부, 기둥)를 하나 걸러 번갈아 가면서 아래층으로 시공하며 이후에는 남은 수직부재를 동시에 시공하는 공사방법을 제공하여 공사기간을 단축할 수 있도록 한다. 본 발명에 따른 하나 걸러 번갈아 이어지는 역타공법의 공사방법은 흙막이를 설치하고 지하 기둥말뚝을 시공한 후, 지하 1층 터파기 및 지상 1층 바닥을 시공하는 제1단계 ; 지하층 슬라브를 아래층으로 시공하면서 상향 시공되는 지상층 코어부를 지지하기 위하여 지하 1개층 코어부를 먼저 시공하는 제2단계 ; 지하 수직부재를 하나 걸러 번갈아 가며 하향으로 순타로 1개층씩 시공하는 제3단계 ; 최하층 매트 또는 기초를 시공한 후, 하나걸러 남은 잔여층 지하 부직부재를 동시에 또는 단계별로 순타로 시공하는 단계 ; 로 이루어져 지하 수직부재 공사기간을 단축함으로써 이후의 지상 골조 및 마감공사를 조기에 착수할 수 있게 되어 전체 공사기간을 단축하는 것을 특징으로 한다.
Method for Alternate Basement Vertical Structure Construction Method in Top Down Construction Project
하나 걸러 번갈아 시공되는 역타공법의 지하 수직부재 공사방법
YANG KYUNG OK (Autor:in)
04.01.2021
Patent
Elektronische Ressource
Koreanisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Europäisches Patentamt | 2021
Europäisches Patentamt | 2019
|Special construction method for basement foundation through steel structure alternate construction
Europäisches Patentamt | 2020
|Basement structure spring layer top-down construction method
Europäisches Patentamt | 2023
|