Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Construction of Prestressed Concrete Single-Tee Bridge Superstructures
This report discusses in detail the construction of the first five precast, prestressed concrete, single-tee beam bridge superstructures to be let to contract in Virginia. The data suggest that this single-tee beam enables efficient construction of the superstructures of bridges in the short-span range, because the contractor can move from the bridge seat stage of construction to the forms-in-place stage by erecting beams mass produced at a fabricating plant. Using a 45-ton crane, several men can erect, connect, and overlay the tee beams at the rate of about one 42 ft. x 44 ft. (12.6 m x 13.2 m) span per week. With the addition of precast parapets, superstructure form work at the bridge site is almost eliminated. On-site construction time for the single-tee superstructure is controlled primarily by the time required for the site-cast concrete used in the diaphragms, overlays, and backwalls to attain the design strength. Single-tee bridge construction should be continued in a manner consistent with the conclusions of this report. Some additional research is recommended.
Construction of Prestressed Concrete Single-Tee Bridge Superstructures
This report discusses in detail the construction of the first five precast, prestressed concrete, single-tee beam bridge superstructures to be let to contract in Virginia. The data suggest that this single-tee beam enables efficient construction of the superstructures of bridges in the short-span range, because the contractor can move from the bridge seat stage of construction to the forms-in-place stage by erecting beams mass produced at a fabricating plant. Using a 45-ton crane, several men can erect, connect, and overlay the tee beams at the rate of about one 42 ft. x 44 ft. (12.6 m x 13.2 m) span per week. With the addition of precast parapets, superstructure form work at the bridge site is almost eliminated. On-site construction time for the single-tee superstructure is controlled primarily by the time required for the site-cast concrete used in the diaphragms, overlays, and backwalls to attain the design strength. Single-tee bridge construction should be continued in a manner consistent with the conclusions of this report. Some additional research is recommended.
Construction of Prestressed Concrete Single-Tee Bridge Superstructures
M. M. Sprinkel (Autor:in)
1977
101 pages
Report
Keine Angabe
Englisch
Lifetime Performance Analysis of Existing Prestressed Concrete Bridge Superstructures
British Library Online Contents | 2004
|Lifetime Performance Analysis of Existing Prestressed Concrete Bridge Superstructures
Online Contents | 2004
|Prestressed concrete bridge construction
Engineering Index Backfile | 1965
|Composite concrete bridge superstructures
TIBKAT | 1988
|