A slope of a 50 m deep cut for a federal freeway in Germany began to slide during excavation. By means of a stabilizing fill the slope was temporarily stabilized. Additional explorations and stability analyses resulted in the design of stabilizing measures, consisting of tendons and long drainage holes. In addition, a monitoring program consisting of surface measuring points, anchor load cells, extensometers, inclinometers and piezometers was carried out. Under these conditions, the final excavation of the cut was successfully carried out.
A slope of a 50 m deep cut for a federal freeway in Germany began to slide during excavation. By means of a stabilizing fill the slope was temporarily stabilized. Additional explorations and stability analyses resulted in the design of stabilizing measures, consisting of tendons and long drainage holes. In addition, a monitoring program consisting of surface measuring points, anchor load cells, extensometers, inclinometers and piezometers was carried out. Under these conditions, the final excavation of the cut was successfully carried out.
Stabilization of a Rock Mass Slide
Wittke, Walter (Autor:in)
31.03.2014
16 pages
Aufsatz/Kapitel (Buch)
Elektronische Ressource
Deutsch
Failure mechanism and stabilization of a basalt rock slide with weak layers
British Library Online Contents | 2018
|Failure mechanism and stabilization of a basalt rock slide with weak layers
British Library Online Contents | 2018
|Criteria for Initiation of Slide, Rock, and Slide-Rock Rigid-Body Modes