The coupling of project delivery methods and contract strategies for public building projects in Ethiopia
The purpose of this paper is to use Delphi technique to assess the applicability of coupling various project delivery methods (PDMs) and contract strategies (CSs) for delivery of public building projects (PBP) in Ethiopia.
To achieve the objective of this research, an online Delphi study was designed, conducted and analyzed using various statistical procedures. Results were compared to CII’s project delivery and CS (PDCS) tool, a US-based PDM selection tool.
This study converged in the third round signifying a consensus on the importance of design–build and construction manager at risk as alternatives to design–bid–build. In addition, “controlling schedule growth” was deemed to be a major performance measure that needs to be considered for PBP in Ethiopia, a result consistent with the outcomes from CII’s PDCS tool.
Among existing studies, none to the best of the authors’ knowledge has focused on a holistic approach to identify the most appropriate pairings of PDMs and CSs for PBP which was critically needed due to the magnitude and high stakes of these projects. This research is a steppingstone toward gaining knowledge on how to approach these types of projects in fast-growing environments thirsty for new building projects such as in Ethiopia.
The coupling of project delivery methods and contract strategies for public building projects in Ethiopia
The purpose of this paper is to use Delphi technique to assess the applicability of coupling various project delivery methods (PDMs) and contract strategies (CSs) for delivery of public building projects (PBP) in Ethiopia.
To achieve the objective of this research, an online Delphi study was designed, conducted and analyzed using various statistical procedures. Results were compared to CII’s project delivery and CS (PDCS) tool, a US-based PDM selection tool.
This study converged in the third round signifying a consensus on the importance of design–build and construction manager at risk as alternatives to design–bid–build. In addition, “controlling schedule growth” was deemed to be a major performance measure that needs to be considered for PBP in Ethiopia, a result consistent with the outcomes from CII’s PDCS tool.
Among existing studies, none to the best of the authors’ knowledge has focused on a holistic approach to identify the most appropriate pairings of PDMs and CSs for PBP which was critically needed due to the magnitude and high stakes of these projects. This research is a steppingstone toward gaining knowledge on how to approach these types of projects in fast-growing environments thirsty for new building projects such as in Ethiopia.
The coupling of project delivery methods and contract strategies for public building projects in Ethiopia
Legesse, Abay (author) / Nejat, Ali (author) / Ghebrab, Tewodros (author)
Construction Innovation ; 25 ; 400-418
2025-02-11
19 pages
Article (Journal)
Electronic Resource
English
Relative Effectiveness of Project Delivery and Contract Strategies
British Library Online Contents | 2006
|IMPACT OF VARIATION ORDERS ON PUBLIC BUILDING PROJECTS IN ADDIS ABABA, ETHIOPIA
BASE | 2017
|Project delivery methods for large scale building projects: a case study
British Library Conference Proceedings | 1998
|Project delivery and contract strategy for district energy projects - a lifecycle approach
BASE | 2012
|