Project buffer sizing and dynamic buffer consumption algorithm in power generation construction
The aim of this research is to propose a buffer sizing and buffer controlling algorithm (BSCA) as a heuristic algorithm for calculating project buffer and feeding buffers as well as dynamic controlling of buffer consumption in different phases of a wind power plant project in order to achieve a more realistic project duration.
The BSCA algorithm has two main phases of planning and buffer sizing and construction and buffer consumption. Project buffer and feeding buffers are determined in the planning and buffer sizing phase, and their consumption is controlled in the construction and buffer consumption phase. The heuristic algorithm was coded and run in MATLAB software. The sensitivity analysis was conducted to show the BSCA influence on project implementation. Then, to evaluate the BSCA algorithm, inputs from this project were run through several algorithms recently presented by researchers. Finally, the data of 20 projects previously accomplished by the company were applied to compare the proposed algorithm.
The results show that BSCA heuristic algorithm outperformed the other algorithms as it shortened the projects' durations. The average project completion time using the BSCA algorithm was reduced by about 15% compared to the previous average project completion time.
The proposed BSCA algorithm determines both the project buffer and feeding buffers and simultaneously controls their consumption in a dynamic way.
Project buffer sizing and dynamic buffer consumption algorithm in power generation construction
The aim of this research is to propose a buffer sizing and buffer controlling algorithm (BSCA) as a heuristic algorithm for calculating project buffer and feeding buffers as well as dynamic controlling of buffer consumption in different phases of a wind power plant project in order to achieve a more realistic project duration.
The BSCA algorithm has two main phases of planning and buffer sizing and construction and buffer consumption. Project buffer and feeding buffers are determined in the planning and buffer sizing phase, and their consumption is controlled in the construction and buffer consumption phase. The heuristic algorithm was coded and run in MATLAB software. The sensitivity analysis was conducted to show the BSCA influence on project implementation. Then, to evaluate the BSCA algorithm, inputs from this project were run through several algorithms recently presented by researchers. Finally, the data of 20 projects previously accomplished by the company were applied to compare the proposed algorithm.
The results show that BSCA heuristic algorithm outperformed the other algorithms as it shortened the projects' durations. The average project completion time using the BSCA algorithm was reduced by about 15% compared to the previous average project completion time.
The proposed BSCA algorithm determines both the project buffer and feeding buffers and simultaneously controls their consumption in a dynamic way.
Project buffer sizing and dynamic buffer consumption algorithm in power generation construction
BSCA algorithm
Zohrehvandi, Shakib (author) / Khalilzadeh, Mohammad (author) / Amiri, Maghsoud (author) / Shadrokh, Shahram (author)
Engineering, Construction and Architectural Management ; 29 ; 716-738
2021-03-17
23 pages
Article (Journal)
Electronic Resource
English
Buffer Sizing in Construction Scheduling Using Critical Chain Project Management
Springer Verlag | 2022
|Data-driven project buffer sizing in critical chains
Elsevier | 2022
|APRT-FMEA buffer sizing method in scheduling of a wind farm construction project
Emerald Group Publishing | 2019
|Buffer Sizing in Critical Chain Project Management by Brittle Risk Entropy
DOAJ | 2022
|