Achieving sustainability through integrating risk management into the architectural design process
The purpose of this paper is to develop a framework integrating risk management (RM) into the architectural design process (ADP) as an approach for delivering sustainable construction projects.
A research methodology, which consisted of literature review and field study, is designed to accomplish four objectives. First, to provide a comprehensive literature review of the concepts of sustainability, ADP and RM. Second, to present and synthesis the results of two relevant studies focused on identifying, quantifying and classifying the risks associated with ADP; and investigating the perception and application of Egyptian architectural design firms (ADFs) towards integrating RM into ADP as an approach for delivering sustainable construction projects. Third, to develop a framework that integrates RM into ADP towards delivering sustainable construction projects. Finally, to draw conclusions and recommendations to improve the practice of delivering sustainable construction projects among ADFs, construction professionals and governmental authorities.
ADP is a fundamental phase of the construction process because the decisions adopted during this phase affect the project performance throughout its life cycle. While RM is widely applied in different sectors of the construction industry, its application in ADP received scant attention in construction literature. The research identified 18 key risks that affect the sustainable delivery of construction projects during ADP. The architect, the client and the project manager are the highest ranked responsible parties for the occurrence of these key risks. The field study highlighted the need to develop a framework to facilitate integrating RM into ADP.
This paper focused only on the integration of RM into ADP.
The conducted literature review and field study provided an in-depth understanding of the key risks that affect the sustainable delivery of construction projects during ADP. Through its five stages, the proposed framework is expected to serve as a foundation for integrating RM into ADP as an approach for delivering sustainable projects. This ideology has received scant attention in construction literature. The developed framework represents a synthesis that is novel and creative in thought and adds value to the knowledge in a manner that has not previously occurred.
Achieving sustainability through integrating risk management into the architectural design process
The purpose of this paper is to develop a framework integrating risk management (RM) into the architectural design process (ADP) as an approach for delivering sustainable construction projects.
A research methodology, which consisted of literature review and field study, is designed to accomplish four objectives. First, to provide a comprehensive literature review of the concepts of sustainability, ADP and RM. Second, to present and synthesis the results of two relevant studies focused on identifying, quantifying and classifying the risks associated with ADP; and investigating the perception and application of Egyptian architectural design firms (ADFs) towards integrating RM into ADP as an approach for delivering sustainable construction projects. Third, to develop a framework that integrates RM into ADP towards delivering sustainable construction projects. Finally, to draw conclusions and recommendations to improve the practice of delivering sustainable construction projects among ADFs, construction professionals and governmental authorities.
ADP is a fundamental phase of the construction process because the decisions adopted during this phase affect the project performance throughout its life cycle. While RM is widely applied in different sectors of the construction industry, its application in ADP received scant attention in construction literature. The research identified 18 key risks that affect the sustainable delivery of construction projects during ADP. The architect, the client and the project manager are the highest ranked responsible parties for the occurrence of these key risks. The field study highlighted the need to develop a framework to facilitate integrating RM into ADP.
This paper focused only on the integration of RM into ADP.
The conducted literature review and field study provided an in-depth understanding of the key risks that affect the sustainable delivery of construction projects during ADP. Through its five stages, the proposed framework is expected to serve as a foundation for integrating RM into ADP as an approach for delivering sustainable projects. This ideology has received scant attention in construction literature. The developed framework represents a synthesis that is novel and creative in thought and adds value to the knowledge in a manner that has not previously occurred.
Achieving sustainability through integrating risk management into the architectural design process
Othman, Ayman Ahmed Ezzat (author) / Abdelwahab, Nermeen Mohamed Amin (author)
Journal of Engineering, Design and Technology ; 16 ; 25-43
2018-02-05
19 pages
Article (Journal)
Electronic Resource
English
Integrating Architectural Science Understanding into the Architectural Design Process
Taylor & Francis Verlag | 1991
|Achieving Sustainability through Integrated Design
British Library Online Contents | 2007
Integrating building shape optimization into the architectural design process
Taylor & Francis Verlag | 2020
|