Critical considerations on tower crane layout planning for high-rise modular integrated construction
Modular integrated construction (MiC) is the most advanced off-site construction technology. However, the application of MiC for high-rise buildings is still limited and challenging. One critical issue is tower crane layout planning (TCLP) to guarantee safe and efficient multiple crane-lifts for module installation, which, however, has been insufficiently explored. For filling this knowledge gap, this paper aims to systematically explore the critical considerations on TCLP for high-rise MiC to support contractors in determining the optimal crane layout plan.
This study employed a multimethod strategy. First, previous studies on TCLP and critical features of MiC were reviewed to develop a conceptual model of TCLP considerations. Second, expert interviews with 15 construction planners were conducted to identify the critical TCLP considerations for high-rise MiC. Third, a multicase study with three high-rise MiC projects was undertaken to demonstrate and verify the identified considerations.
The paper characterises critical considerations on TCLP as performance criteria and influencing factors and identifies 7 critical performance criteria and 25 influencing factors for high-rise MiC. Specifically, the features of MiC (e.g. various modularised layout design, heavyweight and large size of modules) were found to significantly affect the crane layout performance (i.e. technical feasibility, safety and economic efficiency).
The paper is the first-of-its-kind study on crane layout planning for high-rise modular buildings, which contributes a two-stage multicriteria decision-making framework integrated with systematic TCLP considerations. The findings should help contractors determine safe and efficient tower crane layout plans for high-rise MiC projects.
Critical considerations on tower crane layout planning for high-rise modular integrated construction
Modular integrated construction (MiC) is the most advanced off-site construction technology. However, the application of MiC for high-rise buildings is still limited and challenging. One critical issue is tower crane layout planning (TCLP) to guarantee safe and efficient multiple crane-lifts for module installation, which, however, has been insufficiently explored. For filling this knowledge gap, this paper aims to systematically explore the critical considerations on TCLP for high-rise MiC to support contractors in determining the optimal crane layout plan.
This study employed a multimethod strategy. First, previous studies on TCLP and critical features of MiC were reviewed to develop a conceptual model of TCLP considerations. Second, expert interviews with 15 construction planners were conducted to identify the critical TCLP considerations for high-rise MiC. Third, a multicase study with three high-rise MiC projects was undertaken to demonstrate and verify the identified considerations.
The paper characterises critical considerations on TCLP as performance criteria and influencing factors and identifies 7 critical performance criteria and 25 influencing factors for high-rise MiC. Specifically, the features of MiC (e.g. various modularised layout design, heavyweight and large size of modules) were found to significantly affect the crane layout performance (i.e. technical feasibility, safety and economic efficiency).
The paper is the first-of-its-kind study on crane layout planning for high-rise modular buildings, which contributes a two-stage multicriteria decision-making framework integrated with systematic TCLP considerations. The findings should help contractors determine safe and efficient tower crane layout plans for high-rise MiC projects.
Critical considerations on tower crane layout planning for high-rise modular integrated construction
Tower crane planning for modular construction
Zhang, Zhiqian (author) / Pan, Wei (author) / Pan, Mi (author)
Engineering, Construction and Architectural Management ; 29 ; 2615-2634
2021-06-18
20 pages
Article (Journal)
Electronic Resource
English
Tower Crane Location Optimization for Heavy Unit Lifting in High-Rise Modular Construction
DOAJ | 2021
|