HYBRID METHOD OF ERECTING A COLD BOX USING PREFABRICATED AND FIELD ERECTED COMPONENTS
A method of erecting a cold box that includes the steps of anchoring at least one column (102) to a foundation (101) in a substantial-ly vertical orientation; anchoring a pipe rack module (103) to the founda-tion in a substantially vertical orientation, wherein the pipe rack module is in close proximity to the at least one column; attaching interconnecting piping between the pipe rack module and the at least one column; anchor-ing at least four corner beams (104) to the edge of the foundation in a sub-stantially vertical orientation; attaching prefabricated panels (105) with bracing to the corner beams, to form an enclosure around the column and piping; and attaching a roof (106) to the enclose is provided.
La présente invention concerne un procédé permettant d'ériger une colonne distillation et comportant les étapes consistant: à ancrer au moins une colonne (102) sur une fondation (101) selon une orientation sensiblement verticale; à ancrer sur la fondation selon une orientation sensiblement verticale un module de nappe de tubes aérienne (103), lequel module se trouvant à proximité de la colonne considérée; à fixer la tuyauterie d'interconnexion entre le module et la colonne; à ancrer au bord de la fondation selon une orientation sensiblement verticale au moins quatre poutrelles de coin (104); à fixer par haubanage aux poutrelles de coin des panneaux préfabriqués (105) de façon à former une enceinte entourant la colonne et la tuyauterie; et à fixer un toit (106) à l'enceinte.
HYBRID METHOD OF ERECTING A COLD BOX USING PREFABRICATED AND FIELD ERECTED COMPONENTS
A method of erecting a cold box that includes the steps of anchoring at least one column (102) to a foundation (101) in a substantial-ly vertical orientation; anchoring a pipe rack module (103) to the founda-tion in a substantially vertical orientation, wherein the pipe rack module is in close proximity to the at least one column; attaching interconnecting piping between the pipe rack module and the at least one column; anchor-ing at least four corner beams (104) to the edge of the foundation in a sub-stantially vertical orientation; attaching prefabricated panels (105) with bracing to the corner beams, to form an enclosure around the column and piping; and attaching a roof (106) to the enclose is provided.
La présente invention concerne un procédé permettant d'ériger une colonne distillation et comportant les étapes consistant: à ancrer au moins une colonne (102) sur une fondation (101) selon une orientation sensiblement verticale; à ancrer sur la fondation selon une orientation sensiblement verticale un module de nappe de tubes aérienne (103), lequel module se trouvant à proximité de la colonne considérée; à fixer la tuyauterie d'interconnexion entre le module et la colonne; à ancrer au bord de la fondation selon une orientation sensiblement verticale au moins quatre poutrelles de coin (104); à fixer par haubanage aux poutrelles de coin des panneaux préfabriqués (105) de façon à former une enceinte entourant la colonne et la tuyauterie; et à fixer un toit (106) à l'enceinte.
HYBRID METHOD OF ERECTING A COLD BOX USING PREFABRICATED AND FIELD ERECTED COMPONENTS
PROCEDE HYBRIDE D'ERECTION D'UNE COLONNE DE DISTILLATION A PARTIR DE COMPOSANTS PREFABRIQUES ET ERIGES SUR SITE
PELTIER STEPHANE (author) / COTE DENIS (author) / HARDY YVES (author) / POULIN GILLES (author)
2017-06-27
Patent
Electronic Resource
English
IPC:
E04H
Gebäude oder ähnliche Bauwerke für besondere Zwecke
,
BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES
/
F25J
LIQUEFACTION, SOLIDIFICATION, OR SEPARATION OF GASES OR GASEOUS MIXTURES BY PRESSURE AND COLD TREATMENT
,
Verflüssigen, Verfestigen oder Trennen von Gasen oder Gasgemischen durch Druck- und Kältebehandlung
HYBRID METHOD OF ERECTING A COLD BOX USING PREFABRICATED AND FIELD ERECTED COMPONENTS
European Patent Office | 2017
Prefabricated pier erecting device, erecting method and obstacle crossing method
European Patent Office | 2020
|Prefabricated pi-shaped beam erecting device and erecting method
European Patent Office | 2023
|