A platform for research: civil engineering, architecture and urbanism
CONTROLLING BACKFLOW FROM DRILLING WITH HOLLOW REBAR AND GROUTING
Backflow during installation of a ground anchor is controlled using a preventer, and the preventer is removed during curing of grout and backflow. A cylinder may be inserted at least partially into a structure, and the preventer placed or attached atop the cylinder. A hollow bar may be extended through the preventer and cylinder into one or more layers of materials beyond the cylinder. Grout may be delivered to the layer(s) through the hollow bar, which may cause a viscous backflow to flow into the cylinder and preventer. During application of the grout, the preventer may be used to control a rate of backflow. After application of the grout, the preventer may put into an open position, and a seal assembly forced down the hollow bar, through an interior cavity of the preventer, to a position below the preventer, after which the preventer may be removed while the grout and backflow cure.
On limite les retours pendant linstallation dun corps mort au moyen dun obturateur antiéruption, puis on enlève ce dernier au cours du durcissement du coulis et du retour. On peut introduire un cylindre au moins partiellement dans une structure et placer ou fixer lobturateur antiéruption par-dessus le cylindre. Une barre creuse peut être introduite dans lobturateur antiéruption et le cylindre jusquà ce quelle pénètre dans au moins une couche de matériau au-delà du cylindre. Le coulis peut être versé dans les couches par lintermédiaire de la barre creuse, ce qui peut causer un retour visqueux dans le cylindre et lobturateur antiéruption. En versant le coulis, on peut contrôler un débit du retour au moyen de lobturateur antiéruption. Une fois le coulis versé, on peut ouvrir lobturateur antiéruption et forcer un ensemble détanchéité au fond de la barre creuse par lintermédiaire dune cavité intérieure dans lobturateur, et ce, jusquà ce que lensemble détanchéité atteigne une position sous celui-ci. On peut ensuite procéder à lenlèvement de lobturateur antiéruption pendant le durcissement du coulis et du retour.
CONTROLLING BACKFLOW FROM DRILLING WITH HOLLOW REBAR AND GROUTING
Backflow during installation of a ground anchor is controlled using a preventer, and the preventer is removed during curing of grout and backflow. A cylinder may be inserted at least partially into a structure, and the preventer placed or attached atop the cylinder. A hollow bar may be extended through the preventer and cylinder into one or more layers of materials beyond the cylinder. Grout may be delivered to the layer(s) through the hollow bar, which may cause a viscous backflow to flow into the cylinder and preventer. During application of the grout, the preventer may be used to control a rate of backflow. After application of the grout, the preventer may put into an open position, and a seal assembly forced down the hollow bar, through an interior cavity of the preventer, to a position below the preventer, after which the preventer may be removed while the grout and backflow cure.
On limite les retours pendant linstallation dun corps mort au moyen dun obturateur antiéruption, puis on enlève ce dernier au cours du durcissement du coulis et du retour. On peut introduire un cylindre au moins partiellement dans une structure et placer ou fixer lobturateur antiéruption par-dessus le cylindre. Une barre creuse peut être introduite dans lobturateur antiéruption et le cylindre jusquà ce quelle pénètre dans au moins une couche de matériau au-delà du cylindre. Le coulis peut être versé dans les couches par lintermédiaire de la barre creuse, ce qui peut causer un retour visqueux dans le cylindre et lobturateur antiéruption. En versant le coulis, on peut contrôler un débit du retour au moyen de lobturateur antiéruption. Une fois le coulis versé, on peut ouvrir lobturateur antiéruption et forcer un ensemble détanchéité au fond de la barre creuse par lintermédiaire dune cavité intérieure dans lobturateur, et ce, jusquà ce que lensemble détanchéité atteigne une position sous celui-ci. On peut ensuite procéder à lenlèvement de lobturateur antiéruption pendant le durcissement du coulis et du retour.
CONTROLLING BACKFLOW FROM DRILLING WITH HOLLOW REBAR AND GROUTING
REGULATION DU REFOULEMENT PROVENANT DU FORAGE A L`AIDE D`UNE BARRE D`ARMATURE CREUSE ET D`UN COULIS
ASCHENBROICH HORST K (author)
2022-02-22
Patent
Electronic Resource
English
IPC:
E02D
FOUNDATIONS
,
Gründungen
Controlling backflow from drilling with hollow rebar and grouting
European Patent Office | 2021
|CONTROLLING BACKFLOW FROM DRILLING WITH HOLLOW REBAR AND GROUTING
European Patent Office | 2020
|HOLLOW REBAR FOR POST-GROUTING THE BASE OF REINFORCED CONCRETE DRILLED SHAFTS
European Patent Office | 2022
|