Method for widening soft soil roadbed in frozen soil area
The invention discloses a method for widening a soft soil roadbed in a frozen soil area, which comprises the following steps of: S1, digging back the edge of an old roadbed to form a trapezoidal connecting end surface; S2, marking a pile sinking point in a to-be-broadened roadbed area on the edge of the old roadbed, enabling an immersed tube to go deep into the soft soil foundation by utilizing hammering equipment; throwing stone into the structural hole of the immersed tube to be vibrated and tamped such that the pile sinking operation is completed, wherein the to-be-broadened roadbed comprises a connection area and a common area; S3, laying a mattress layer on the to-be-broadened roadbed subjected to the pile sinking operation; and S4, arranging geogrids on the mattress layer. Accordingto the method, the technical problems that due to the fact that the geological liquid degree of the soft roadbed is high, disturbance of a conventional compaction treatment method to the foundation islarge, the stability of the lap joint structure of the new roadbed and the old roadbed is affected, construction is difficult to conduct in the frozen soil period, and construction needs to be conducted after shutdown and waiting for proper time are solved.
本发明申请公开了一种冻土区软土路基的拓宽方法,包括步骤S1.在旧路基的边沿进行回挖处理,形成梯形的连接端面;步骤S2.在所述旧路基边沿的待拓宽路基区域标记沉桩点,利用锤击设备将沉管深入软土地基中;将石料投入所述沉管的结构孔洞中震动捣实,完成沉桩作业;其中所述待拓宽路基区域包括衔接区域和普通区域;步骤S3.在完成沉桩作业的待拓宽路基上铺设褥垫层;步骤S4.在所述褥垫层上设置土工格栅。本发明申请解决了由于软弱路基地质液态程度较高,常规的压实处理方法对地基的扰动较大,对新旧路基搭接的结构的稳定性造成影响,且涉及到冻土期的时候难以进行施工,不得不停工等待合适的时间来进行施工技术问题。
Method for widening soft soil roadbed in frozen soil area
The invention discloses a method for widening a soft soil roadbed in a frozen soil area, which comprises the following steps of: S1, digging back the edge of an old roadbed to form a trapezoidal connecting end surface; S2, marking a pile sinking point in a to-be-broadened roadbed area on the edge of the old roadbed, enabling an immersed tube to go deep into the soft soil foundation by utilizing hammering equipment; throwing stone into the structural hole of the immersed tube to be vibrated and tamped such that the pile sinking operation is completed, wherein the to-be-broadened roadbed comprises a connection area and a common area; S3, laying a mattress layer on the to-be-broadened roadbed subjected to the pile sinking operation; and S4, arranging geogrids on the mattress layer. Accordingto the method, the technical problems that due to the fact that the geological liquid degree of the soft roadbed is high, disturbance of a conventional compaction treatment method to the foundation islarge, the stability of the lap joint structure of the new roadbed and the old roadbed is affected, construction is difficult to conduct in the frozen soil period, and construction needs to be conducted after shutdown and waiting for proper time are solved.
本发明申请公开了一种冻土区软土路基的拓宽方法,包括步骤S1.在旧路基的边沿进行回挖处理,形成梯形的连接端面;步骤S2.在所述旧路基边沿的待拓宽路基区域标记沉桩点,利用锤击设备将沉管深入软土地基中;将石料投入所述沉管的结构孔洞中震动捣实,完成沉桩作业;其中所述待拓宽路基区域包括衔接区域和普通区域;步骤S3.在完成沉桩作业的待拓宽路基上铺设褥垫层;步骤S4.在所述褥垫层上设置土工格栅。本发明申请解决了由于软弱路基地质液态程度较高,常规的压实处理方法对地基的扰动较大,对新旧路基搭接的结构的稳定性造成影响,且涉及到冻土期的时候难以进行施工,不得不停工等待合适的时间来进行施工技术问题。
Method for widening soft soil roadbed in frozen soil area
冻土区软土路基的拓宽方法
LI JIANXI (author) / XIE QUANFU (author) / LI HAORAN (author) / QIU WEICHAO (author) / ZHOU BIAO (author) / MA XIAOBING (author)
2020-04-17
Patent
Electronic Resource
Chinese
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
European Patent Office | 2023
|Foam polymerization light soil widening roadbed construction method
European Patent Office | 2024
|Deep soft soil high filling roadbed widening structure and construction method thereof
European Patent Office | 2024
|Roadbed structure in frozen soil area and construction method
European Patent Office | 2023
|