Support structure for sectional installation of large diameter and extra-long pipeline across roof and construction method
The invention relates to industrial and civil buildings, in particular to a support structure for sectional installation of a large diameter and extra-long pipeline across a roof and a construction method. The support structure comprises a left plant column and a right plant column in the inner sides of the walls on the two sides of a plant, the left plant column and the right plant column are respectively provided with a left crane beam and a right crane beam, the left crane beam and the right crane beam are respectively provided with a left column and a right column, the upper ends of the left column and the right column extend out of a roof of a workshop, a beam is installed at the upper ends of the left column and the right column, pipe brackets are installed on the beam, and middle pipelines are placed on the pipe brackets. The problem that the site of an old plant area is narrow and a large crane cannot stand and lift is solved; segmental hoisting of large diameter and extra-longpipelines has high construction safety; a crane of smaller tonnage can meet construction requirements; original plant columns are fully utilized, the height of a support is reduced, and the amount ofthe support is saved; and the construction period is shortened, and the construction cost is lowered.
本发明涉及工业与民用建筑,特别是一种跨屋面大直径超长管道分段安装的支撑结构及施工方法。包括厂房两侧墙体内侧的左厂房柱和右厂房柱,左厂房柱和右厂房柱上分别安装左吊车梁和右吊车梁,左吊车梁和右吊车梁上分别安装左立柱和右立柱,左立柱和右立柱的上端伸出车间屋顶,左立柱和右立柱的上端安装横梁,横梁上安装管托,中间管道置于在该管托上。解决了旧厂区场地狭小,大型吊车无法站位及起吊的问题;大直径超长管道分段吊装,施工安全性高;较小吨位的的吊车即可以满足施工要求;充分利用原有厂房柱子,减少支架高度,节省支架用量;缩短工期,降低施工成本。
Support structure for sectional installation of large diameter and extra-long pipeline across roof and construction method
The invention relates to industrial and civil buildings, in particular to a support structure for sectional installation of a large diameter and extra-long pipeline across a roof and a construction method. The support structure comprises a left plant column and a right plant column in the inner sides of the walls on the two sides of a plant, the left plant column and the right plant column are respectively provided with a left crane beam and a right crane beam, the left crane beam and the right crane beam are respectively provided with a left column and a right column, the upper ends of the left column and the right column extend out of a roof of a workshop, a beam is installed at the upper ends of the left column and the right column, pipe brackets are installed on the beam, and middle pipelines are placed on the pipe brackets. The problem that the site of an old plant area is narrow and a large crane cannot stand and lift is solved; segmental hoisting of large diameter and extra-longpipelines has high construction safety; a crane of smaller tonnage can meet construction requirements; original plant columns are fully utilized, the height of a support is reduced, and the amount ofthe support is saved; and the construction period is shortened, and the construction cost is lowered.
本发明涉及工业与民用建筑,特别是一种跨屋面大直径超长管道分段安装的支撑结构及施工方法。包括厂房两侧墙体内侧的左厂房柱和右厂房柱,左厂房柱和右厂房柱上分别安装左吊车梁和右吊车梁,左吊车梁和右吊车梁上分别安装左立柱和右立柱,左立柱和右立柱的上端伸出车间屋顶,左立柱和右立柱的上端安装横梁,横梁上安装管托,中间管道置于在该管托上。解决了旧厂区场地狭小,大型吊车无法站位及起吊的问题;大直径超长管道分段吊装,施工安全性高;较小吨位的的吊车即可以满足施工要求;充分利用原有厂房柱子,减少支架高度,节省支架用量;缩短工期,降低施工成本。
Support structure for sectional installation of large diameter and extra-long pipeline across roof and construction method
跨屋面大直径超长管道分段安装的支撑结构及施工方法
MA JIYE (author) / REN WEIYI (author) / JIN GUOSHUAI (author)
2020-05-08
Patent
Electronic Resource
Chinese
Synchronous construction method of steelmaking plant and roof large-diameter pipeline
European Patent Office | 2021
|European Patent Office | 2023
|Large-span oval daylighting roof steel structure support-free installation construction method
European Patent Office | 2024
|Large-diameter concrete pipeline installation auxiliary device and installation method
European Patent Office | 2024
|