Guide wall construction method and guide wall construction structure
The invention relates to the technical field of guide wall construction methods, in particular to a guide wall construction method and a guide wall construction structure. The method comprises the following steps that a groove is excavated, specifically, after surveying and setting out are conducted, the groove is excavated by combining mechanical earth cutting and manual finishing; steel bars arebound, specifically, after the groove is excavated, vertical steel bars are fixed, then horizontal steel bars are bound, and finally drag hooks and cushion blocks are installed; guide wall templatesused for pouring guide wall concrete are erected in the groove; the guide wall concrete is poured; and the guide wall templates are disassembled, and the interior of the guide wall is supported insidethe groove. The invention aims to provide the guide wall construction method and the guide wall construction structure, and by means of the guide wall construction method, the problems that in the prior art, the quality of the prepared guide wall cannot be guaranteed by means of an existing guide wall preparation method, the utilization requirements cannot be met, the cost is increased, raw materials are wasted, and the construction period is prolonged are solved.
本发明涉及导墙施工方法技术领域,尤其是涉及一种导墙施工方法及导墙施工结构;包括如下步骤:开挖沟槽:测量放线后,采用机械挖土和人工修整相结合的方式开挖沟槽;绑扎钢筋:沟槽挖设完毕后,先固定竖向钢筋,再绑扎水平钢筋,最后安装拉钩和垫块;在沟槽中支设用以浇筑导墙混凝土的导墙模板;浇筑导墙混凝土;拆除导墙模板,在沟槽内对导墙内部进行支撑。本发明的目的在于提供一种导墙施工方法及导墙施工结构,通过导墙施工方法以解决现有技术中存在现有的导墙制备方法无法保证制备导墙的质量,达不到使用要求,增加了成本,浪费原材料,延长了施工周期。
Guide wall construction method and guide wall construction structure
The invention relates to the technical field of guide wall construction methods, in particular to a guide wall construction method and a guide wall construction structure. The method comprises the following steps that a groove is excavated, specifically, after surveying and setting out are conducted, the groove is excavated by combining mechanical earth cutting and manual finishing; steel bars arebound, specifically, after the groove is excavated, vertical steel bars are fixed, then horizontal steel bars are bound, and finally drag hooks and cushion blocks are installed; guide wall templatesused for pouring guide wall concrete are erected in the groove; the guide wall concrete is poured; and the guide wall templates are disassembled, and the interior of the guide wall is supported insidethe groove. The invention aims to provide the guide wall construction method and the guide wall construction structure, and by means of the guide wall construction method, the problems that in the prior art, the quality of the prepared guide wall cannot be guaranteed by means of an existing guide wall preparation method, the utilization requirements cannot be met, the cost is increased, raw materials are wasted, and the construction period is prolonged are solved.
本发明涉及导墙施工方法技术领域,尤其是涉及一种导墙施工方法及导墙施工结构;包括如下步骤:开挖沟槽:测量放线后,采用机械挖土和人工修整相结合的方式开挖沟槽;绑扎钢筋:沟槽挖设完毕后,先固定竖向钢筋,再绑扎水平钢筋,最后安装拉钩和垫块;在沟槽中支设用以浇筑导墙混凝土的导墙模板;浇筑导墙混凝土;拆除导墙模板,在沟槽内对导墙内部进行支撑。本发明的目的在于提供一种导墙施工方法及导墙施工结构,通过导墙施工方法以解决现有技术中存在现有的导墙制备方法无法保证制备导墙的质量,达不到使用要求,增加了成本,浪费原材料,延长了施工周期。
Guide wall construction method and guide wall construction structure
一种导墙施工方法及导墙施工结构