Steel pipe stand column positioning device and positioning construction method thereof
The invention discloses a steel pipe stand column positioning device and a positioning construction method thereof. The steel pipe stand column positioning device comprises a positioning frame and a working section, wherein a steel pipe column penetrates through a stand column hole of the positioning frame to enter a designed hole well, the working section is connected with the steel pipe column,an adjusting device on the positioning frame adjusts the perpendicularity of the steel pipe column through the working section, the steel pipe column is positioned by using the positioning frame and apositioner, and the perpendicularity of the steel pipe column is adjusted by the working section and a telescopic oil cylinder. According to the steel pipe stand column positioning device and the positioning construction method thereof, accurate positioning of the steel pipe column in a narrow construction site is realized, the positioning precision is high, stable and controllable, deviation iseasy to correct, the operation method is simple and convenient, the technical difficulty is low, tool equipment can be recycled, the cost is low, the economic benefit is obvious, super concrete capable of keeping plasticity for a long time is newly arranged, the problems that the steel pipe column is inserted into a pile foundation to be resisted, and pile pulling is difficult are solved, the steel pipe column construction method is changed into a positioning frame rear-inserting method, concrete pouring is carried out on the interior of the steel pipe column in advance, the positioning frameis subjected to line production, the construction efficiency is improved, and the construction progress is accelerated.
本发明公开了一种钢管立柱定位装置及其定位施工方法,包括定位架与工作节,钢管柱穿过定位架的立柱孔进入设计孔井,工作节连接钢管柱,定位架上的调节装置通过工作节调节钢管柱的垂直度,使用定位架与定位器实现钢管柱定位,工作节与伸缩油缸调整钢管柱的垂直度。本发明实现在狭小施工场地进行准确地钢管柱定位,定位精度高、稳定、可控、易纠偏,操作方法简单方便,技术难度低,工装设备可循环使用,成本低廉,经济效益明显,新配置可长时间保持塑性的超混凝混凝土,解决钢管柱插入桩基受抗,拔桩困难的问题,将钢管柱施工方法改为定位架后插法,提前对钢管柱内部进行混凝土浇筑,定位架流水作业,提高施工效率,加快施工进度。
Steel pipe stand column positioning device and positioning construction method thereof
The invention discloses a steel pipe stand column positioning device and a positioning construction method thereof. The steel pipe stand column positioning device comprises a positioning frame and a working section, wherein a steel pipe column penetrates through a stand column hole of the positioning frame to enter a designed hole well, the working section is connected with the steel pipe column,an adjusting device on the positioning frame adjusts the perpendicularity of the steel pipe column through the working section, the steel pipe column is positioned by using the positioning frame and apositioner, and the perpendicularity of the steel pipe column is adjusted by the working section and a telescopic oil cylinder. According to the steel pipe stand column positioning device and the positioning construction method thereof, accurate positioning of the steel pipe column in a narrow construction site is realized, the positioning precision is high, stable and controllable, deviation iseasy to correct, the operation method is simple and convenient, the technical difficulty is low, tool equipment can be recycled, the cost is low, the economic benefit is obvious, super concrete capable of keeping plasticity for a long time is newly arranged, the problems that the steel pipe column is inserted into a pile foundation to be resisted, and pile pulling is difficult are solved, the steel pipe column construction method is changed into a positioning frame rear-inserting method, concrete pouring is carried out on the interior of the steel pipe column in advance, the positioning frameis subjected to line production, the construction efficiency is improved, and the construction progress is accelerated.
本发明公开了一种钢管立柱定位装置及其定位施工方法,包括定位架与工作节,钢管柱穿过定位架的立柱孔进入设计孔井,工作节连接钢管柱,定位架上的调节装置通过工作节调节钢管柱的垂直度,使用定位架与定位器实现钢管柱定位,工作节与伸缩油缸调整钢管柱的垂直度。本发明实现在狭小施工场地进行准确地钢管柱定位,定位精度高、稳定、可控、易纠偏,操作方法简单方便,技术难度低,工装设备可循环使用,成本低廉,经济效益明显,新配置可长时间保持塑性的超混凝混凝土,解决钢管柱插入桩基受抗,拔桩困难的问题,将钢管柱施工方法改为定位架后插法,提前对钢管柱内部进行混凝土浇筑,定位架流水作业,提高施工效率,加快施工进度。
Steel pipe stand column positioning device and positioning construction method thereof
一种钢管立柱定位装置及其定位施工方法
DUAN JINGCHUAN (author) / XI XIAOQING (author) / WU XIAOBIN (author) / HE RONGLIU (author) / WANG MINGMING (author) / YAN LIMING (author) / LIU SHANGXU (author)
2020-09-18
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Reverse construction method steel stand column positioning device and positioning method
European Patent Office | 2016
|Temporary stand column positioning device and temporary stand column positioning construction method
European Patent Office | 2021
|Positioning verticality adjusting device and steel pipe column positioning construction method
European Patent Office | 2024
|Steel pipe plane position positioning method of steel pipe stand column pile
European Patent Office | 2024
|