A platform for research: civil engineering, architecture and urbanism
Steel pipe column positioning construction method
According to the technical scheme, the steel pipe column positioning construction method is characterized by comprising the steps that S1, the earth surface of a pile hole is leveled and hardened to serve as a construction base plane; s2, a positioning device used for conducting radial positioning on the steel pipe column is installed on the construction base face, the positioning device is leveled, and the center axis of the positioning device is aligned with the center axis of the pile hole; s3, a construction frame body is installed on the construction base plane, and a straightening device is arranged on the construction frame body; s4, a laser device is installed at the center position in the steel pipe column, and a light sensing piece used for detecting laser emitted by the laser device is arranged on the installation frame; s5, the steel pipe column is inserted into the pile hole through the positioning device, the steel pipe column is slowly put down, the vertical pair of the steel pipe column is corrected through the straightening device, and laser emitted by the laser device is made to always irradiate the light sensing piece; when the steel pipe column is installed, the steel pipe column can be conveniently and well installed and positioned.
本发明涉及一种钢管柱定位施工方法,其技术方案的要点是所述方法包括,步骤S1,对桩孔地表进行整平硬化,作为施工基面;步骤S2,在施工基面上安装用于对钢管柱进行径向定位的定位装置,并且对定位装置进行调平,使定位装置的中心轴与桩孔的中心轴相对齐;步骤S3,在施工基面上安装施工架体,施工架体上设置有校直装置;步骤S4,在钢管柱内部中心位置安装激光器,在安装架上设置用于对激光器发出激光进行检测的感光片;步骤S5,将钢管柱由定位装置插入到桩孔中,缓慢对钢管柱进行下放,通过校直装置对钢管柱的垂直对进行校正,使激光器发出的激光始终照射在感光片上;本发明能够在对钢管柱进行安装时,方便良好的对钢管柱进行安装定位。
Steel pipe column positioning construction method
According to the technical scheme, the steel pipe column positioning construction method is characterized by comprising the steps that S1, the earth surface of a pile hole is leveled and hardened to serve as a construction base plane; s2, a positioning device used for conducting radial positioning on the steel pipe column is installed on the construction base face, the positioning device is leveled, and the center axis of the positioning device is aligned with the center axis of the pile hole; s3, a construction frame body is installed on the construction base plane, and a straightening device is arranged on the construction frame body; s4, a laser device is installed at the center position in the steel pipe column, and a light sensing piece used for detecting laser emitted by the laser device is arranged on the installation frame; s5, the steel pipe column is inserted into the pile hole through the positioning device, the steel pipe column is slowly put down, the vertical pair of the steel pipe column is corrected through the straightening device, and laser emitted by the laser device is made to always irradiate the light sensing piece; when the steel pipe column is installed, the steel pipe column can be conveniently and well installed and positioned.
本发明涉及一种钢管柱定位施工方法,其技术方案的要点是所述方法包括,步骤S1,对桩孔地表进行整平硬化,作为施工基面;步骤S2,在施工基面上安装用于对钢管柱进行径向定位的定位装置,并且对定位装置进行调平,使定位装置的中心轴与桩孔的中心轴相对齐;步骤S3,在施工基面上安装施工架体,施工架体上设置有校直装置;步骤S4,在钢管柱内部中心位置安装激光器,在安装架上设置用于对激光器发出激光进行检测的感光片;步骤S5,将钢管柱由定位装置插入到桩孔中,缓慢对钢管柱进行下放,通过校直装置对钢管柱的垂直对进行校正,使激光器发出的激光始终照射在感光片上;本发明能够在对钢管柱进行安装时,方便良好的对钢管柱进行安装定位。
Steel pipe column positioning construction method
一种钢管柱定位施工方法
ZHAO PENG (author) / LI HONGLIANG (author) / ZHANG LIJUN (author) / XIAO XIAN (author) / ZHU LEIMIN (author) / LIU JINMING (author) / YU JIANWEN (author)
2022-08-05
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
European Patent Office | 2023
|Positioning verticality adjusting device and steel pipe column positioning construction method
European Patent Office | 2024
|Steel pipe stand column positioning device and positioning construction method thereof
European Patent Office | 2020
|Column bottom embedded steel pipe pile positioning construction method
European Patent Office | 2021
|Steel pipe pile embedded type column foot foundation bolt positioning construction method
European Patent Office | 2021
|