Construction method for controlling verticality of building outer wall insulation formwork integrated plate
The invention relates to the technical field of building construction, in particular to a construction method for controlling verticality of a building outer wall insulation formwork integrated plate.The method comprises the following steps that S1, the insulation formwork integrated plate is installed according to a scheme, and a connecting piece and a reinforcing steel bar are bond and positioned through a binding steel wire; S2, a split bolt is installed; S3, formwork main and secondary ridges are installed; S4, a square pipe is installed on the outer wall side, and inner and outer formworks and main and secondary back ridges are fixed; S5, cement mortar cushion blocks are alternately arranged at the intersection position of a splicing seam and the main back ridge; S6, a cement mortarsurface is constructed; and S7, anti-cracking mortar is pressed into an alkali-resistant gridding cloth. The construction method is easy to operate, improves the construction efficiency, effectively controls the verticality of the insulation formwork integrated plate and ensures the construction quality. The construction method is mainly applied to outer wall insulation formwork integrated plate verticality control laying.
本发明涉及建筑施工技术领域,更具体而言,涉及建筑外墙保模一体板垂平度控制施工方法。包括以下步骤:S1、将保模一体板根据方案安装,并用绑扎钢丝将连接件与钢筋绑扎定位;S2、安装对拉螺栓;S3、安装模板主次楞;S4、外墙侧安装方管,固定内外模板、主次背楞;S5、在拼缝与主背楞相交处交替布置水泥砂浆垫块;S6、施工水泥砂浆面;S7、抗裂砂浆压入耐碱网格布。本发明的施工方法操作简单,提高了施工效率,有效控制了保模一体板的垂平度,保证了施工质量。本发明主要应用在外墙保模一体板垂平度控制铺设。
Construction method for controlling verticality of building outer wall insulation formwork integrated plate
The invention relates to the technical field of building construction, in particular to a construction method for controlling verticality of a building outer wall insulation formwork integrated plate.The method comprises the following steps that S1, the insulation formwork integrated plate is installed according to a scheme, and a connecting piece and a reinforcing steel bar are bond and positioned through a binding steel wire; S2, a split bolt is installed; S3, formwork main and secondary ridges are installed; S4, a square pipe is installed on the outer wall side, and inner and outer formworks and main and secondary back ridges are fixed; S5, cement mortar cushion blocks are alternately arranged at the intersection position of a splicing seam and the main back ridge; S6, a cement mortarsurface is constructed; and S7, anti-cracking mortar is pressed into an alkali-resistant gridding cloth. The construction method is easy to operate, improves the construction efficiency, effectively controls the verticality of the insulation formwork integrated plate and ensures the construction quality. The construction method is mainly applied to outer wall insulation formwork integrated plate verticality control laying.
本发明涉及建筑施工技术领域,更具体而言,涉及建筑外墙保模一体板垂平度控制施工方法。包括以下步骤:S1、将保模一体板根据方案安装,并用绑扎钢丝将连接件与钢筋绑扎定位;S2、安装对拉螺栓;S3、安装模板主次楞;S4、外墙侧安装方管,固定内外模板、主次背楞;S5、在拼缝与主背楞相交处交替布置水泥砂浆垫块;S6、施工水泥砂浆面;S7、抗裂砂浆压入耐碱网格布。本发明的施工方法操作简单,提高了施工效率,有效控制了保模一体板的垂平度,保证了施工质量。本发明主要应用在外墙保模一体板垂平度控制铺设。
Construction method for controlling verticality of building outer wall insulation formwork integrated plate
建筑外墙保模一体板垂平度控制施工方法
BAI LINFANG (author) / FAN YUNHUA (author)
2020-09-29
Patent
Electronic Resource
Chinese
IPC:
E04B
Allgemeine Baukonstruktionen
,
GENERAL BUILDING CONSTRUCTIONS
Construction method of outer wall non-dismantling thermal insulation formwork
European Patent Office | 2023
|Building outer wall formwork-removal-free decorative plate and building outer wall structure
European Patent Office | 2024
|Integrated prefabricated wall plate verticality adjusting device
European Patent Office | 2020
|Building outer wall formwork-removal-free decorative plate and building outer wall structure
European Patent Office | 2023
|