Synchronous pre-buried forming construction method for finished electric box along with main body structure
The invention relates to the field of building construction, in particular to a synchronous pre-buried forming construction method for a finished electric box along with a main body structure. The synchronous pre-buried forming construction method comprises the following steps of 1) box body positioning, 2) finished electric box processing, 3) measuring and setting-out, 4) electric box mounting, 5) positioning size reexamining, 6) concrete pouring and 7) clearing out finished products and conducting production. By means of the method for synchronous construction of the finished electric box and a shear wall structure, an original complex process is simplified, construction is carried out in advance during the main body structure period, and the electrical construction burden in the later period of a project is reduced.
本发明涉及建筑施工领域,具体涉及一种成品电箱随主体结构同步预埋成型施工方法,包括以下步骤:1)箱体定位;2)成品电箱加工;3)测量放线;4)电箱安装;5)复核定位尺寸;6)混凝土浇筑与7)清掏成品及保护,本发明提供的成品电箱与剪力墙结构同步施工方法,将原有的复杂工序简单化,并在主体结构期间提前施工,减轻工程后期电气施工负担。
Synchronous pre-buried forming construction method for finished electric box along with main body structure
The invention relates to the field of building construction, in particular to a synchronous pre-buried forming construction method for a finished electric box along with a main body structure. The synchronous pre-buried forming construction method comprises the following steps of 1) box body positioning, 2) finished electric box processing, 3) measuring and setting-out, 4) electric box mounting, 5) positioning size reexamining, 6) concrete pouring and 7) clearing out finished products and conducting production. By means of the method for synchronous construction of the finished electric box and a shear wall structure, an original complex process is simplified, construction is carried out in advance during the main body structure period, and the electrical construction burden in the later period of a project is reduced.
本发明涉及建筑施工领域,具体涉及一种成品电箱随主体结构同步预埋成型施工方法,包括以下步骤:1)箱体定位;2)成品电箱加工;3)测量放线;4)电箱安装;5)复核定位尺寸;6)混凝土浇筑与7)清掏成品及保护,本发明提供的成品电箱与剪力墙结构同步施工方法,将原有的复杂工序简单化,并在主体结构期间提前施工,减轻工程后期电气施工负担。
Synchronous pre-buried forming construction method for finished electric box along with main body structure
一种成品电箱随主体结构同步预埋成型施工方法
HUANG YICHUN (author) / LI WEI (author) / YANG XIAOHUI (author) / ZHANG CONG (author) / LIU YANPING (author) / WU SHANGQUAN (author) / WEI ZHIFENG (author) / KANG LONGHUA (author) / YANG SHAOMING (author) / LI YUANKAI (author)
2020-10-16
Patent
Electronic Resource
Chinese
Main body structure and waterstop synchronous construction method
European Patent Office | 2021
|Anti-displacement construction method for finished support pre-buried groove
European Patent Office | 2021
|Temporary water system pre-buried in main body structure and construction method
European Patent Office | 2024
|Construction process for main body structure of buried sewage treatment plant
European Patent Office | 2023
|Synchronous construction method for external wall panel and main body structure
European Patent Office | 2023
|