Honeycomb cell and graded broken stone composite base construction method
The invention relates to the technical field of composite base construction, and discloses a honeycomb cell and graded broken stone composite base construction method. The method comprises the steps of S1 cleaning and leveling a base; S2 carrying out surveying and setting out on the base; S3 installing and fixing honeycomb cells on the base; S4 mixing graded broken stone, and adjusting the watercontent; S5 paving the graded broken stone on the base; S6 rolling the honeycomb cells paved with the graded broken stone to form a honeycomb cell and graded broken stone composite base. The problemsof insufficient soft soil roadbed bearing capacity, railway roadbed disease treatment, highway, railway and urban road pavement cracks and subsidence and the like can be solved, and meanwhile, ideas and solutions are provided for rapid recovery of pavement traffic of emergency projects such as emergency rescue and disaster relief; the construction efficiency is high; the construction quality is high; and a 'sponge city' function is achieved.
本发明涉及复合基层施工技术领域,公开了一种蜂巢格室与级配碎石复合基层施工方法,包括步骤:S1、基地清理与整平;S2、对基地进行测量放线;S3、在基地上安装与固定蜂巢格室;S4、拌合级配碎石及调整含水率;S5、将级配碎石摊铺在基地上;S6、对上面摊铺有级配碎石的蜂巢格室进行碾压,形成蜂巢格室与级配碎石复合基层。可解决软土路基承载力不足、铁路基床病害治理,以及高速公路、铁路和城市道路路面裂缝和沉陷等问题,同时为抢险救灾类应急项目路面交通的快速恢复提供了思路和解决方案;施工效率高;施工质量高;具有“海绵城市”功能。
Honeycomb cell and graded broken stone composite base construction method
The invention relates to the technical field of composite base construction, and discloses a honeycomb cell and graded broken stone composite base construction method. The method comprises the steps of S1 cleaning and leveling a base; S2 carrying out surveying and setting out on the base; S3 installing and fixing honeycomb cells on the base; S4 mixing graded broken stone, and adjusting the watercontent; S5 paving the graded broken stone on the base; S6 rolling the honeycomb cells paved with the graded broken stone to form a honeycomb cell and graded broken stone composite base. The problemsof insufficient soft soil roadbed bearing capacity, railway roadbed disease treatment, highway, railway and urban road pavement cracks and subsidence and the like can be solved, and meanwhile, ideas and solutions are provided for rapid recovery of pavement traffic of emergency projects such as emergency rescue and disaster relief; the construction efficiency is high; the construction quality is high; and a 'sponge city' function is achieved.
本发明涉及复合基层施工技术领域,公开了一种蜂巢格室与级配碎石复合基层施工方法,包括步骤:S1、基地清理与整平;S2、对基地进行测量放线;S3、在基地上安装与固定蜂巢格室;S4、拌合级配碎石及调整含水率;S5、将级配碎石摊铺在基地上;S6、对上面摊铺有级配碎石的蜂巢格室进行碾压,形成蜂巢格室与级配碎石复合基层。可解决软土路基承载力不足、铁路基床病害治理,以及高速公路、铁路和城市道路路面裂缝和沉陷等问题,同时为抢险救灾类应急项目路面交通的快速恢复提供了思路和解决方案;施工效率高;施工质量高;具有“海绵城市”功能。
Honeycomb cell and graded broken stone composite base construction method
一种蜂巢格室与级配碎石复合基层施工方法
LIU ZHONG (author) / LIU TIEJUN (author) / WENG JIANYONG (author) / KONG XIANGMING (author) / LIN XUAN (author) / HE GUANGFENG (author)
2020-10-27
Patent
Electronic Resource
Chinese
Honeycomb cell for graded broken stone base construction
European Patent Office | 2020
|Honeycomb graded broken stone composite base layer construction method
European Patent Office | 2024
|Construction method of graded broken stone and cement composite packing layer
European Patent Office | 2015
|Graded broken stone saturated watertight vibration construction technology
European Patent Office | 2023
|Construction method of retaining wall graded broken stone inverted filter
European Patent Office | 2024
|