A platform for research: civil engineering, architecture and urbanism
Renovation transformation construction method for large building roof
The invention relates to a renovation transformation construction method for a large building roof, and belongs to the technical field of renovation and transformation of a building roof. The method comprises the following steps of S1, removing a roof protection layer to a waterproof layer, and reserving the complete waterproof layer; S2, detecting the positions of roof panels, cutting and separating along seams between adjacent roof panels, simultaneously cutting and separating welding positions between the roof panels to be removed and a steel beam, in-situ mounting a new roof panel immediately after one old roof panel is removed by using the method of dismounting and mounting therewith, and filling seams of adjacent newly-mounted roof panels with mortar; and S3, after replacement with arow of new roof panels is completed, making a first waterproof layer adhering to the row of new roof panels, and making the first waterproof layer in lap joint with the waterproof layer of the old roof and sealing. When the old roof panels are replaced with the new roof panels, the complete waterproof structure of the roof can be ensured all the time, the indoor leakage is avoided during rainfallor snowfall, and normal use of a building is ensured.
本发明涉及一种大型建筑屋面翻新改造施工方法,属于建筑屋面翻新改造的技术领域,包括以下步骤:S1、剔除屋面保护层至防水层处,并保留完整的防水层;S2、探测屋面板的位置,沿着相邻屋面板的拼缝处进行切割分离,同时将待拆除屋面板与钢梁焊接处切割分离,采用“随拆随安”的方法,将旧屋面板拆除之后,立即在原位安装新屋面板,安装的相邻新屋面板之间的拼缝砂浆灌缝处理;S3、在一行新屋面板更换完成后,在其上粘接第一道防水层,第一道防水层与旧屋面防水层搭接并密封。在旧屋面板和新屋面板进行更换时,能够始终保证屋面完整的防水结构,避免降雨或者降雪时向室内渗漏,保证建筑的正常使用。
Renovation transformation construction method for large building roof
The invention relates to a renovation transformation construction method for a large building roof, and belongs to the technical field of renovation and transformation of a building roof. The method comprises the following steps of S1, removing a roof protection layer to a waterproof layer, and reserving the complete waterproof layer; S2, detecting the positions of roof panels, cutting and separating along seams between adjacent roof panels, simultaneously cutting and separating welding positions between the roof panels to be removed and a steel beam, in-situ mounting a new roof panel immediately after one old roof panel is removed by using the method of dismounting and mounting therewith, and filling seams of adjacent newly-mounted roof panels with mortar; and S3, after replacement with arow of new roof panels is completed, making a first waterproof layer adhering to the row of new roof panels, and making the first waterproof layer in lap joint with the waterproof layer of the old roof and sealing. When the old roof panels are replaced with the new roof panels, the complete waterproof structure of the roof can be ensured all the time, the indoor leakage is avoided during rainfallor snowfall, and normal use of a building is ensured.
本发明涉及一种大型建筑屋面翻新改造施工方法,属于建筑屋面翻新改造的技术领域,包括以下步骤:S1、剔除屋面保护层至防水层处,并保留完整的防水层;S2、探测屋面板的位置,沿着相邻屋面板的拼缝处进行切割分离,同时将待拆除屋面板与钢梁焊接处切割分离,采用“随拆随安”的方法,将旧屋面板拆除之后,立即在原位安装新屋面板,安装的相邻新屋面板之间的拼缝砂浆灌缝处理;S3、在一行新屋面板更换完成后,在其上粘接第一道防水层,第一道防水层与旧屋面防水层搭接并密封。在旧屋面板和新屋面板进行更换时,能够始终保证屋面完整的防水结构,避免降雨或者降雪时向室内渗漏,保证建筑的正常使用。
Renovation transformation construction method for large building roof
大型建筑屋面翻新改造施工方法
JI YAO (author) / TAO YINGQI (author) / CHEN ZHAOCUI (author) / CHEN YONGFU (author) / CHI MINGLONG (author) / SONG HUI (author)
2020-10-30
Patent
Electronic Resource
Chinese
Construction method for waterproof renovation of railway concrete roof
European Patent Office | 2021
|WALL OF BUILDING STRUCTURE, BUILDING MATERIAL PANEL FOR ROOF RENOVATION
European Patent Office | 2023
|Construction method for waterproof renovation of railway metal roof
European Patent Office | 2021
|Large-span old factory building roof renewal and transformation construction method
European Patent Office | 2024
|