Assembled power transmission tower base structure and construction method thereof
The invention discloses an assembled power transmission tower base structure and a construction method thereof, and relates to the technical field of assembled construction. The base comprises a precast pile base, a precast bearing platform, a precast hollow thin-wall circular pier and a power transmission tower construction platform. The pile base and the bearing platform are connected by adopting a bolt-grouting method, and the other pre-fabricated members are connected through flange plates. The assembled power transmission tower base structure has the following advantages that all structures are pre-fabricated members, the construction period is short, and the base can decrease the height of a power transmission tower and is suitable for building of power transmission towers in mountains large in height difference.
本发明公开一种装配式输电塔基础结构及其施工方法,涉及到装配式施工技术领域。该基础包括预制桩基础、预制承台、预制空心薄壁圆墩和输电塔施工平台。桩基础与承台采用螺栓加注浆的方法连接,其他预制件之间的连接均采用法兰盘。本发明具有以下优点:所有结构均为预制件,施工工期短;该基础能够减小输电塔的高度,适应于高低起伏大的山区的输电塔建设。
Assembled power transmission tower base structure and construction method thereof
The invention discloses an assembled power transmission tower base structure and a construction method thereof, and relates to the technical field of assembled construction. The base comprises a precast pile base, a precast bearing platform, a precast hollow thin-wall circular pier and a power transmission tower construction platform. The pile base and the bearing platform are connected by adopting a bolt-grouting method, and the other pre-fabricated members are connected through flange plates. The assembled power transmission tower base structure has the following advantages that all structures are pre-fabricated members, the construction period is short, and the base can decrease the height of a power transmission tower and is suitable for building of power transmission towers in mountains large in height difference.
本发明公开一种装配式输电塔基础结构及其施工方法,涉及到装配式施工技术领域。该基础包括预制桩基础、预制承台、预制空心薄壁圆墩和输电塔施工平台。桩基础与承台采用螺栓加注浆的方法连接,其他预制件之间的连接均采用法兰盘。本发明具有以下优点:所有结构均为预制件,施工工期短;该基础能够减小输电塔的高度,适应于高低起伏大的山区的输电塔建设。
Assembled power transmission tower base structure and construction method thereof
一种装配式输电塔基础结构及其施工方法
ZHANG YONGJIE (author) / CAO JUN (author) / HUANG JINXIN (author) / HUANG ZHENG (author) / LIU TAO (author) / LI ZIFENG (author) / HUANG WANDONG (author)
2020-11-24
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Power transmission tower and construction method thereof
European Patent Office | 2024
|European Patent Office | 2021
|Power transmission line emergency rescue iron tower base construction method