Kerb mechanized operation construction method
The invention discloses a kerb mechanized operation construction method. The kerb mechanized operation construction method comprises the following steps that S1, construction preparation is carried out, and continuous and effective construction can be ensured; S2, measuring and setting out are carried out; S3, the kerb is subjected to slotting; S4, curb stone is installed, and the site is cleaned;and S5, curing and finished product protection are carried out, specifically, finished product protection and curing are conducted through plastic film covering, the curing period of the kerb is notshorter than 3 d, and collision should be strictly prevented in the period. According to the kerb mechanized operation construction method, a traditional construction method is reformed and innovated,the slotting depth is guaranteed through a longitudinal slope control system, the width of adjacent block joints is controlled through improved clamping pieces, construction is simplified through advanced instruments and equipment, the construction straightness of the kerb is guaranteed, full joint filling is guaranteed through small tools, and other measures are adopted, so that the constructionquality is effectively improved, the construction cost is saved, and the method has remarkable economic benefits and social benefits, and has very wide application prospects.
本发明公开了一种路缘石机械化作业施工工法,所述施工工法包含以下步骤:步骤一:施工准备,确保施工连续有效进行;步骤二:测量放样;步骤三:路缘石开槽;步骤四:路缘石安装,并清理场地;步骤五:养生及成品保护,采用塑料薄膜覆盖进行成品保护并养护,路缘石的养护期不得少于3d,期间应严防碰撞。该路缘石机械化作业施工工法,对传统的施工方法进行改革创新,通过纵坡控制系统保证开槽深度、改进夹片控制邻块缝宽、利用先进仪器设备简化施工保证路缘石施工平直度、利用小工具保证填缝的饱满充实等措施有效提高了施工质量,节约了施工成本;具有显著的经济效益和社会效益,应有前景十分广阔。
Kerb mechanized operation construction method
The invention discloses a kerb mechanized operation construction method. The kerb mechanized operation construction method comprises the following steps that S1, construction preparation is carried out, and continuous and effective construction can be ensured; S2, measuring and setting out are carried out; S3, the kerb is subjected to slotting; S4, curb stone is installed, and the site is cleaned;and S5, curing and finished product protection are carried out, specifically, finished product protection and curing are conducted through plastic film covering, the curing period of the kerb is notshorter than 3 d, and collision should be strictly prevented in the period. According to the kerb mechanized operation construction method, a traditional construction method is reformed and innovated,the slotting depth is guaranteed through a longitudinal slope control system, the width of adjacent block joints is controlled through improved clamping pieces, construction is simplified through advanced instruments and equipment, the construction straightness of the kerb is guaranteed, full joint filling is guaranteed through small tools, and other measures are adopted, so that the constructionquality is effectively improved, the construction cost is saved, and the method has remarkable economic benefits and social benefits, and has very wide application prospects.
本发明公开了一种路缘石机械化作业施工工法,所述施工工法包含以下步骤:步骤一:施工准备,确保施工连续有效进行;步骤二:测量放样;步骤三:路缘石开槽;步骤四:路缘石安装,并清理场地;步骤五:养生及成品保护,采用塑料薄膜覆盖进行成品保护并养护,路缘石的养护期不得少于3d,期间应严防碰撞。该路缘石机械化作业施工工法,对传统的施工方法进行改革创新,通过纵坡控制系统保证开槽深度、改进夹片控制邻块缝宽、利用先进仪器设备简化施工保证路缘石施工平直度、利用小工具保证填缝的饱满充实等措施有效提高了施工质量,节约了施工成本;具有显著的经济效益和社会效益,应有前景十分广阔。
Kerb mechanized operation construction method
一种路缘石机械化作业施工工法
JI WENYUAN (author) / YAN KUN (author) / HU YONGGUANG (author) / ZHANG CHUANGXIAO (author) / SHANG GUANGQI (author) / ZHANG XIHANG (author) / RU GUOLIANG (author) / LEI PENGZHEN (author) / ZHANG YONGGANG (author) / WU LEI (author)
2020-12-11
Patent
Electronic Resource
Chinese
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
/
B28D
Bearbeiten von Stein oder steinähnlichen Werkstoffen
,
WORKING STONE OR STONE-LIKE MATERIALS
/
G01C
Messen von Entfernungen, Höhen, Neigungen oder Richtungen
,
MEASURING DISTANCES, LEVELS OR BEARINGS
PREFABRICATED FORM FOR KERB CONSTRUCTION AND CONSTRUCTION METHOD OF KERB USING THE SAME
European Patent Office | 2018
|Kerb of assembled self-drainage asphalt pavement and construction method of kerb
European Patent Office | 2020
|