Combined steel beam steel formwork laying device and laying method thereof
The invention discloses a combined steel beam steel formwork laying device and a laying method thereof. The technical problem that in the prior art, when a combined steel beam steel formwork is installed and constructed, installation efficiency is low due to the fact that an installation site is limited, and the overall construction progress is affected is solved. The laying device comprises a conveying frame and a winch; wheels are arranged on the conveying frame, and limiting rails matching the wheels and used for guiding are arranged on the top face of the combined steel beam. The laying method comprises the steps that firstly, the laying device is installed at the top of the combined steel beam, then the steel formwork is hoisted to the laying device, then the winch is started to pullthe frame to the steel formwork installation working condition, and finally the steel formwork is unloaded to the installation position through an adjustable bearing mechanism. The laying device is simple in structure, scientific and reasonable in design and convenient to use, combined steel beam formwork installation can be effectively and efficiently completed under the working condition that the installation site is limited, and therefore the overall construction progress of steel structure construction is guaranteed.
本发明公开了一种组合钢梁钢模板铺设装置及其铺设方法,解决现有技术组合钢梁钢模板安装施工时因安装场地受限导致安装效率低下从而影响整体施工进度的技术问题。铺设装置包括输送车架、以及卷扬机;输送车架上设有车轮,组合钢梁顶面上设有与车轮相适配用于导向的限位轨。铺设方法为首先在组合钢梁顶部安装铺设装置,再将钢模板吊装至铺设装置上,然后启动卷扬机将车架牵引到钢模板安装工况处,最后通过可调节承托机构将钢模板卸载至安装位置。本发明结构简单、设计科学合理,使用方便,其可以有效在安装场地受限的工况高效完成组合钢梁钢模板安装,从而保证钢结构施工的响整体施工进度。
Combined steel beam steel formwork laying device and laying method thereof
The invention discloses a combined steel beam steel formwork laying device and a laying method thereof. The technical problem that in the prior art, when a combined steel beam steel formwork is installed and constructed, installation efficiency is low due to the fact that an installation site is limited, and the overall construction progress is affected is solved. The laying device comprises a conveying frame and a winch; wheels are arranged on the conveying frame, and limiting rails matching the wheels and used for guiding are arranged on the top face of the combined steel beam. The laying method comprises the steps that firstly, the laying device is installed at the top of the combined steel beam, then the steel formwork is hoisted to the laying device, then the winch is started to pullthe frame to the steel formwork installation working condition, and finally the steel formwork is unloaded to the installation position through an adjustable bearing mechanism. The laying device is simple in structure, scientific and reasonable in design and convenient to use, combined steel beam formwork installation can be effectively and efficiently completed under the working condition that the installation site is limited, and therefore the overall construction progress of steel structure construction is guaranteed.
本发明公开了一种组合钢梁钢模板铺设装置及其铺设方法,解决现有技术组合钢梁钢模板安装施工时因安装场地受限导致安装效率低下从而影响整体施工进度的技术问题。铺设装置包括输送车架、以及卷扬机;输送车架上设有车轮,组合钢梁顶面上设有与车轮相适配用于导向的限位轨。铺设方法为首先在组合钢梁顶部安装铺设装置,再将钢模板吊装至铺设装置上,然后启动卷扬机将车架牵引到钢模板安装工况处,最后通过可调节承托机构将钢模板卸载至安装位置。本发明结构简单、设计科学合理,使用方便,其可以有效在安装场地受限的工况高效完成组合钢梁钢模板安装,从而保证钢结构施工的响整体施工进度。
Combined steel beam steel formwork laying device and laying method thereof
一种组合钢梁钢模板铺设装置及其铺设方法
WANG XIAO (author) / YU BO (author) / JIANG YOURONG (author) / LIU LIMING (author) / CHEN LUO (author)
2021-01-01
Patent
Electronic Resource
Chinese
IPC:
E01D
BRIDGES
,
Brücken
Pedestrian refined steel formwork for metro and laying method of pedestrian refined steel formwork
European Patent Office | 2023
|European Patent Office | 2023
|Building pouring formwork connector and formwork laying construction method
European Patent Office | 2023
|