Construction method for laying anti-sticking waterproof coiled material on basement raft in advance
In order to effectively prevent an anti-sticking waterproof coiled material from being scratched or scalded, effectively reduce the construction cost and increase the waterproof quality when steel bars are bound and the steel bars and steel plates are welded, the invention provides a construction method for laying the anti-sticking waterproof coiled material on a basement raft in advance. The construction method comprises the following steps of (1) constructing a cushion layer; (2) cleaning a base layer, paying off and positioning; (3) laying the waterproof coiled material; (4) performing acceptance check by checking personnel; (5) constructing reinforcement engineering of a raft foundation after the acceptance check is qualified; and (6) laying waterproof sponge in the construction process of the reinforcement engineering of the raft foundation. According to the construction method, the construction cost is effectively reduced, and the waterproof quality is increased.
为了在进行绑扎钢筋和焊接钢筋、钢板等工作时,能够有效的防止反粘防水卷材被划伤或烫伤,同时还有效的节约了施工成本和提高了防水质量,本发明提供一种地下室筏板预铺反粘防水卷材施工方法,该施工方法包括如下步骤:第一步:垫层施工;第二步:基层清理、放线定位;第三步:铺设防水卷材;第四步:通过验收人员进行验收工作;第五步:验收合格后,进行筏板基础钢筋工程施工;第六步:在筏板基础钢筋工程施工过程中。本发明的还有效的节约了施工成本和提高了防水质量。
Construction method for laying anti-sticking waterproof coiled material on basement raft in advance
In order to effectively prevent an anti-sticking waterproof coiled material from being scratched or scalded, effectively reduce the construction cost and increase the waterproof quality when steel bars are bound and the steel bars and steel plates are welded, the invention provides a construction method for laying the anti-sticking waterproof coiled material on a basement raft in advance. The construction method comprises the following steps of (1) constructing a cushion layer; (2) cleaning a base layer, paying off and positioning; (3) laying the waterproof coiled material; (4) performing acceptance check by checking personnel; (5) constructing reinforcement engineering of a raft foundation after the acceptance check is qualified; and (6) laying waterproof sponge in the construction process of the reinforcement engineering of the raft foundation. According to the construction method, the construction cost is effectively reduced, and the waterproof quality is increased.
为了在进行绑扎钢筋和焊接钢筋、钢板等工作时,能够有效的防止反粘防水卷材被划伤或烫伤,同时还有效的节约了施工成本和提高了防水质量,本发明提供一种地下室筏板预铺反粘防水卷材施工方法,该施工方法包括如下步骤:第一步:垫层施工;第二步:基层清理、放线定位;第三步:铺设防水卷材;第四步:通过验收人员进行验收工作;第五步:验收合格后,进行筏板基础钢筋工程施工;第六步:在筏板基础钢筋工程施工过程中。本发明的还有效的节约了施工成本和提高了防水质量。
Construction method for laying anti-sticking waterproof coiled material on basement raft in advance
一种地下室筏板预铺反粘防水卷材施工方法
WANG JINGFENG (author) / WANG SHAOFEI (author) / ZHU JIANGFENG (author) / XIONG BO (author) / JIANG ZHIYUN (author)
2021-02-09
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Basement bottom plate pre-laying anti-sticking TPO waterproof coiled material construction method
European Patent Office | 2020
|European Patent Office | 2024
|Coiled material waterproof laying equipment and coiled material waterproof laying method
European Patent Office | 2021
|Basement raft foundation waterproof roll construction method based on empty laying method
European Patent Office | 2021
|