Novel steel hanging box cofferdam manufacturing process based on Larsen steel sheet pile
The invention relates to a novel steel hanging box cofferdam manufacturing process based on a Larsen steel sheet pile. The novel steel hanging box cofferdam manufacturing process is characterized by comprising the following specific steps of S1, manufacturing of a steel bottom plate; S2, manufacturing of side plates; S3, manufacturing of hangers; S4, assembling of the steel bottom plate and lowerhanger units; S5, assembling of the hangers; S6, mounting of ring beam brackets; S7, assembling of the side plates; S8, primary bottom sealing and water pumping; and S9, secondary bottom sealing. According to the novel steel hanging box cofferdam manufacturing process, the structure of the Larsen steel sheet pile is adopted as a side edge module structure of a steel hanging box cofferdam, and sideedge modules of the structure are high in strength, light and good in water stopping performance; assembling and disassembling are easy; the turnover performance is high, the cost is low, the applicability to deep water is high, multiple internal supports are arranged, and the enough strength requirement is guaranteed; and in addition, a concrete structure is poured on a bottom plate module, compared with a bottom plate of a steel structure, the advantage of being low in economic cost is achieved, and the profile steel structure is easy to machine and assemble; machining is fast, and the period is short; and the applicability is high, and trepanning is easy.
本发明涉及一种基于拉森钢板桩的新型钢吊箱围堰制造工艺,其特征在于:具体工艺如下:S1:钢底板的制造;S2:侧板的制造;S3:吊挂的制造;S4:钢底板及下吊挂单元的拼装;S5:吊挂的拼装;S6:圈梁牛腿的安装;S7:侧板的拼装;S8:一次封底及抽水;S9:二次封底;本发明中采用拉森钢板桩的结构作为钢吊箱围堰的侧边模块结构,该结构的侧边模块高强度,轻型,止水性好;拼装,拆除简易;周转性高,成本低,对深水的适用性强且内部支撑多,保证了足够的强度要求;此外,在底板模块上浇筑混凝土结构,相比于钢结构的底板,就具有经济成本低的优点,且本发明的型钢结构易加工、易于拼装;加工快,周期短;适用性强,开孔容易。
Novel steel hanging box cofferdam manufacturing process based on Larsen steel sheet pile
The invention relates to a novel steel hanging box cofferdam manufacturing process based on a Larsen steel sheet pile. The novel steel hanging box cofferdam manufacturing process is characterized by comprising the following specific steps of S1, manufacturing of a steel bottom plate; S2, manufacturing of side plates; S3, manufacturing of hangers; S4, assembling of the steel bottom plate and lowerhanger units; S5, assembling of the hangers; S6, mounting of ring beam brackets; S7, assembling of the side plates; S8, primary bottom sealing and water pumping; and S9, secondary bottom sealing. According to the novel steel hanging box cofferdam manufacturing process, the structure of the Larsen steel sheet pile is adopted as a side edge module structure of a steel hanging box cofferdam, and sideedge modules of the structure are high in strength, light and good in water stopping performance; assembling and disassembling are easy; the turnover performance is high, the cost is low, the applicability to deep water is high, multiple internal supports are arranged, and the enough strength requirement is guaranteed; and in addition, a concrete structure is poured on a bottom plate module, compared with a bottom plate of a steel structure, the advantage of being low in economic cost is achieved, and the profile steel structure is easy to machine and assemble; machining is fast, and the period is short; and the applicability is high, and trepanning is easy.
本发明涉及一种基于拉森钢板桩的新型钢吊箱围堰制造工艺,其特征在于:具体工艺如下:S1:钢底板的制造;S2:侧板的制造;S3:吊挂的制造;S4:钢底板及下吊挂单元的拼装;S5:吊挂的拼装;S6:圈梁牛腿的安装;S7:侧板的拼装;S8:一次封底及抽水;S9:二次封底;本发明中采用拉森钢板桩的结构作为钢吊箱围堰的侧边模块结构,该结构的侧边模块高强度,轻型,止水性好;拼装,拆除简易;周转性高,成本低,对深水的适用性强且内部支撑多,保证了足够的强度要求;此外,在底板模块上浇筑混凝土结构,相比于钢结构的底板,就具有经济成本低的优点,且本发明的型钢结构易加工、易于拼装;加工快,周期短;适用性强,开孔容易。
Novel steel hanging box cofferdam manufacturing process based on Larsen steel sheet pile
一种基于拉森钢板桩的新型钢吊箱围堰制造工艺
LIU LIANGLIANG (author) / FU LUNPENG (author) / MAO YAYING (author) / CHENG DONG (author)
2021-03-12
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Larsen steel sheet pile cofferdam and construction method thereof
European Patent Office | 2020
|Simple water stopping method for Larsen steel sheet pile cofferdam
European Patent Office | 2022
|Larsen steel sheet pile and high-pressure jet grouting pile combined cofferdam construction method
European Patent Office | 2021
|Larsen steel sheet pile cofferdam construction method for underwater deep riprap layer area
European Patent Office | 2021
|