Advanced grouting method for tunnel face of cement-rich rock stratum
The invention provides an advanced grouting method for a tunnel face of a cement-rich rock stratum. The advanced grouting method comprises the following steps that (1) advanced geological forecast is conducted; (2) the tunnel face of the cement-rich rock stratum is subjected to grouting design, and a target grouting reinforcement area is determined; (3) monitoring points are arranged in the target grouting reinforcement area; (4) a grouting stopping wall is poured, and advanced grouting hole positions and advanced pipe shed hole positions are designed; (5) advanced grouting and advanced pipe shed drilling operation are conducted; (6) advanced grouting liquid and advanced pipe shed grouting liquid are prepared; (7) advanced grouting construction is conducted; and (8) advanced pipe shed construction is conducted. According to the advanced grouting method for the tunnel face of the cement-rich rock stratum, the tunnel face is subjected to advanced grouting, effective reinforcement treatment is conducted, the construction risk is avoided, the construction efficiency is improved, and the construction cost is reduced.
一种富水泥岩地层隧道掌子面超前注浆方法,包括以下步骤:(1)进行超前地质预报;(2)富水泥岩地层的掌子面注浆设计,确定目标注浆加固区域;(3)在目标注浆加固区域布设监测点;(4)浇注止浆墙,设计超前注浆孔位和超前管棚孔位;(5)实施超前注浆和超前管棚钻孔作业;(6)制备超前注浆液和超前管棚注浆液;(7)超前注浆施工;(8)超前管棚施工。本发明通过对掌子面进行超前注浆,进行有效加固治理,规避施工风险,提高施工效率,降低施工成本。
Advanced grouting method for tunnel face of cement-rich rock stratum
The invention provides an advanced grouting method for a tunnel face of a cement-rich rock stratum. The advanced grouting method comprises the following steps that (1) advanced geological forecast is conducted; (2) the tunnel face of the cement-rich rock stratum is subjected to grouting design, and a target grouting reinforcement area is determined; (3) monitoring points are arranged in the target grouting reinforcement area; (4) a grouting stopping wall is poured, and advanced grouting hole positions and advanced pipe shed hole positions are designed; (5) advanced grouting and advanced pipe shed drilling operation are conducted; (6) advanced grouting liquid and advanced pipe shed grouting liquid are prepared; (7) advanced grouting construction is conducted; and (8) advanced pipe shed construction is conducted. According to the advanced grouting method for the tunnel face of the cement-rich rock stratum, the tunnel face is subjected to advanced grouting, effective reinforcement treatment is conducted, the construction risk is avoided, the construction efficiency is improved, and the construction cost is reduced.
一种富水泥岩地层隧道掌子面超前注浆方法,包括以下步骤:(1)进行超前地质预报;(2)富水泥岩地层的掌子面注浆设计,确定目标注浆加固区域;(3)在目标注浆加固区域布设监测点;(4)浇注止浆墙,设计超前注浆孔位和超前管棚孔位;(5)实施超前注浆和超前管棚钻孔作业;(6)制备超前注浆液和超前管棚注浆液;(7)超前注浆施工;(8)超前管棚施工。本发明通过对掌子面进行超前注浆,进行有效加固治理,规避施工风险,提高施工效率,降低施工成本。
Advanced grouting method for tunnel face of cement-rich rock stratum
一种富水泥岩地层隧道掌子面超前注浆方法
LIU XIANG (author) / DENG XIAOWEI (author) / LIU FEIXIANG (author) / XIE XIAOBO (author) / LI JIAN (author) / LIU HUAPING (author) / XU JUNWEI (author) / CHEN MIN (author) / LIU DE'AN (author) / YANG WENGUO (author)
2021-04-09
Patent
Electronic Resource
Chinese
Weak stratum tunnel advanced deep-hole grouting reinforcement material
European Patent Office | 2016
|Rock stratum grouting plug and bottom-to-top visual grouting method
European Patent Office | 2024
|European Patent Office | 2020
|