Construction method of concrete-filled steel tube pile foundation and concrete-filled steel tube pile foundation
The invention relates to a construction method of a concrete-filled steel tube pile foundation and the concrete-filled steel tube pile foundation. The construction method comprises the steps that a steel tube pile is placed at a preset position of a river bed surface, and the steel tube pile is inserted downwards from the top of the steel tube pile until the steel tube pile cannot sink; impact pore forming is conducted in the steel tube pile; the steel tube pile continues to be inserted until the steel tube pile cannot sink; impact pore forming and insertion of the steel tube pile are conducted alternately until the bottom end of the steel tube pile reaches the designed depth; and concrete is poured into the steel tube pile. According to the construction method of the concrete-filled steel tube pile foundation and the concrete-filled steel tube pile foundation, under the condition of complex geology, the steel tube pile can be smoothly inserted into soil for pile sinking, the bearing capacity of the concrete-filled steel tube pile foundation is good, and the friction pile stress requirement and the end bearing pile stress condition can be met.
本发明涉及一种钢管混凝土桩基的施工方法及钢管混凝土桩基,其包括:在河床面的预设位置放置钢管桩,并于所述钢管桩的顶部向下插打所述钢管桩至无法下沉;在所述钢管桩的内部冲击造孔;继续插打所述钢管桩至无法下沉;冲击造孔与插打所述钢管桩交替进行,直至所述钢管桩底端到达设计深度;在所述钢管桩内灌注混凝土。本发明涉及的一种钢管混凝土桩基的施工方法及钢管混凝土桩基,在复杂地质的情况,钢管桩也能顺利入土沉桩,且钢管混凝土桩基的承载力较好,能够达到摩擦桩受力要求和端承桩受力条件。
Construction method of concrete-filled steel tube pile foundation and concrete-filled steel tube pile foundation
The invention relates to a construction method of a concrete-filled steel tube pile foundation and the concrete-filled steel tube pile foundation. The construction method comprises the steps that a steel tube pile is placed at a preset position of a river bed surface, and the steel tube pile is inserted downwards from the top of the steel tube pile until the steel tube pile cannot sink; impact pore forming is conducted in the steel tube pile; the steel tube pile continues to be inserted until the steel tube pile cannot sink; impact pore forming and insertion of the steel tube pile are conducted alternately until the bottom end of the steel tube pile reaches the designed depth; and concrete is poured into the steel tube pile. According to the construction method of the concrete-filled steel tube pile foundation and the concrete-filled steel tube pile foundation, under the condition of complex geology, the steel tube pile can be smoothly inserted into soil for pile sinking, the bearing capacity of the concrete-filled steel tube pile foundation is good, and the friction pile stress requirement and the end bearing pile stress condition can be met.
本发明涉及一种钢管混凝土桩基的施工方法及钢管混凝土桩基,其包括:在河床面的预设位置放置钢管桩,并于所述钢管桩的顶部向下插打所述钢管桩至无法下沉;在所述钢管桩的内部冲击造孔;继续插打所述钢管桩至无法下沉;冲击造孔与插打所述钢管桩交替进行,直至所述钢管桩底端到达设计深度;在所述钢管桩内灌注混凝土。本发明涉及的一种钢管混凝土桩基的施工方法及钢管混凝土桩基,在复杂地质的情况,钢管桩也能顺利入土沉桩,且钢管混凝土桩基的承载力较好,能够达到摩擦桩受力要求和端承桩受力条件。
Construction method of concrete-filled steel tube pile foundation and concrete-filled steel tube pile foundation
一种钢管混凝土桩基的施工方法及钢管混凝土桩基
XIONG CHANGQING (author) / WEI KUI (author) / YANG XIANQUAN (author) / XU YING (author) / JIANG HENG (author) / KAN MINGRUI (author) / SHI MIN (author)
2021-04-20
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
European Patent Office | 2023
|Concrete filled steel tube pile-composite structure bearing platform foundation with damping device
European Patent Office | 2024
|Concrete pouring device for concrete-filled steel tube pile
European Patent Office | 2020
|