Accumulated slippage construction method for pipe trusses in limited space
The invention discloses an accumulative slippage construction method for pipe trusses in a limited space, and belongs to the technical field of building pipe truss steel structure construction. The accumulative slippage construction method comprises 26 trusses including 1st -26th trusses, a gable truss, a connection truss, a overall assembly jig frame, a component manufacturing jig frame and a temporary fixing device. The accumulated slippage construction method has the advantages that the problem that the pipe trusses in the limited space cannot be installed in a sliding mode from one side according to the conventional sequence is effectively solved, it is guaranteed that the constructable space is utilized to the maximum degree on site, and on the premise that circulation and use of internal materials are not affected, smooth closed transformation construction is conducted on the whole storage place. The accumulated slippage construction method is suitable for installation and construction of the pipe trusses under similar limited space conditions.
一种受限空间内管桁架累积滑移施工方法,属于建筑管桁架钢结构施工技术领域。其中包括:第一桁架1~第二十六桁架、山墙桁架、联系桁架、整体拼装胎架、部件制作胎架、临时固定装置。优点在于:有效解决了受限空间内管桁架不能按常规从一侧顺序滑移安装的问题,保证了现场最大程度利用可施工空间及在不影响内部物资流通使用的前提下对整体储备场所进行封闭改造施工的顺利进行。本方法适用于类似受限空间条件下管桁架的安装施工。
Accumulated slippage construction method for pipe trusses in limited space
The invention discloses an accumulative slippage construction method for pipe trusses in a limited space, and belongs to the technical field of building pipe truss steel structure construction. The accumulative slippage construction method comprises 26 trusses including 1st -26th trusses, a gable truss, a connection truss, a overall assembly jig frame, a component manufacturing jig frame and a temporary fixing device. The accumulated slippage construction method has the advantages that the problem that the pipe trusses in the limited space cannot be installed in a sliding mode from one side according to the conventional sequence is effectively solved, it is guaranteed that the constructable space is utilized to the maximum degree on site, and on the premise that circulation and use of internal materials are not affected, smooth closed transformation construction is conducted on the whole storage place. The accumulated slippage construction method is suitable for installation and construction of the pipe trusses under similar limited space conditions.
一种受限空间内管桁架累积滑移施工方法,属于建筑管桁架钢结构施工技术领域。其中包括:第一桁架1~第二十六桁架、山墙桁架、联系桁架、整体拼装胎架、部件制作胎架、临时固定装置。优点在于:有效解决了受限空间内管桁架不能按常规从一侧顺序滑移安装的问题,保证了现场最大程度利用可施工空间及在不影响内部物资流通使用的前提下对整体储备场所进行封闭改造施工的顺利进行。本方法适用于类似受限空间条件下管桁架的安装施工。
Accumulated slippage construction method for pipe trusses in limited space
一种受限空间内管桁架累积滑移施工方法
RUAN XINWEI (author) / JING KUI (author) / GUO PENGCHENG (author) / ZHENG ZHIKUN (author) / WANG YU (author) / WANG HAICUN (author) / ZHANG HUI (author)
2021-04-27
Patent
Electronic Resource
Chinese
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Steel structure construction method for limiting accumulated slippage
European Patent Office | 2024
|Limited slippage connection structure and construction method of connection structure
European Patent Office | 2023
|Unloading-free in-place method after accumulated slippage of steel structure roof
European Patent Office | 2023
|Slippage construction deviation rectifying device and slippage deviation rectifying method
European Patent Office | 2021
|Curved Space Trusses Formed from Single-Chorded Planar Space Trusses
British Library Conference Proceedings | 1993
|