Stand column construction method in one-column one-pile construction
The invention relates to a stand column construction method in one-column one-pile construction. A first tool column is coaxially assembled at the upper end of a stand column, a clinometer is arranged in the stand column, the stand column is hoisted, first-time perpendicularity adjustment is carried out, the reading of the clinometer when the stand column is perpendicular is recorded as an initial value, a second tool column is coaxially assembled with the upper end of the first tool column in the stand column inserting process, when the stand column is inserted to the elevation, the second tool column is at least partially exposed out of the ground, second-time perpendicularity adjustment is carried out on the stand column by adjusting the second tool column exposed out of the ground, and the second tool column is horizontally moved to enable the center of the second tool column to be consistent with the design center to complete center positioning of the stand column. In the construction process, the assembling type tool columns are used for carrying out inserting construction on the stand column, the hoisting difficulty of the stand column is greatly reduced, the perpendicularity adjusting and center positioning process of the stand column is simplified, and the perpendicular precision and the center positioning precision of the inserted stand column are remarkably improved.
本发明涉及一柱一桩施工中的立柱施工方法,第一工具柱同轴装配在立柱的上端,在立柱内设置测斜仪,吊装立柱,进行第一次调垂,记录立柱垂直时测斜仪读数作为初始值,第二工具柱在立柱插入过程中与第一工具柱的上端同轴装配,第二工具柱在立柱插入至标高时,第二工具柱至少部分露出于地面,通过调节露出于地面的第二工具柱对立柱进行第二次调垂,平移第二工具柱使第二工具柱中心与设计中心一致完成对立柱的中心定位。本发明在施工过程中,使用可装配式工具柱对立柱进行插入施工,大大降低了立柱的吊装难度,简化了立柱的调垂和中心定位的过程,插入的立柱垂直精度、中心定位精度都得到了显著的提高。
Stand column construction method in one-column one-pile construction
The invention relates to a stand column construction method in one-column one-pile construction. A first tool column is coaxially assembled at the upper end of a stand column, a clinometer is arranged in the stand column, the stand column is hoisted, first-time perpendicularity adjustment is carried out, the reading of the clinometer when the stand column is perpendicular is recorded as an initial value, a second tool column is coaxially assembled with the upper end of the first tool column in the stand column inserting process, when the stand column is inserted to the elevation, the second tool column is at least partially exposed out of the ground, second-time perpendicularity adjustment is carried out on the stand column by adjusting the second tool column exposed out of the ground, and the second tool column is horizontally moved to enable the center of the second tool column to be consistent with the design center to complete center positioning of the stand column. In the construction process, the assembling type tool columns are used for carrying out inserting construction on the stand column, the hoisting difficulty of the stand column is greatly reduced, the perpendicularity adjusting and center positioning process of the stand column is simplified, and the perpendicular precision and the center positioning precision of the inserted stand column are remarkably improved.
本发明涉及一柱一桩施工中的立柱施工方法,第一工具柱同轴装配在立柱的上端,在立柱内设置测斜仪,吊装立柱,进行第一次调垂,记录立柱垂直时测斜仪读数作为初始值,第二工具柱在立柱插入过程中与第一工具柱的上端同轴装配,第二工具柱在立柱插入至标高时,第二工具柱至少部分露出于地面,通过调节露出于地面的第二工具柱对立柱进行第二次调垂,平移第二工具柱使第二工具柱中心与设计中心一致完成对立柱的中心定位。本发明在施工过程中,使用可装配式工具柱对立柱进行插入施工,大大降低了立柱的吊装难度,简化了立柱的调垂和中心定位的过程,插入的立柱垂直精度、中心定位精度都得到了显著的提高。
Stand column construction method in one-column one-pile construction
一柱一桩施工中的立柱施工方法
HU XIAOHU (author) / JIANG ZHONGHUA (author)
2021-05-18
Patent
Electronic Resource
Chinese
Stand column construction method in one-column one-pile construction
European Patent Office | 2021
|European Patent Office | 2023
|European Patent Office | 2024
|