ECP wallboard installation construction method
The invention discloses an ECP wallboard installation construction method. The method comprises the following steps that S1, paying-off and installation of embedded parts and keels are conducted; S2, installation of Z-shaped connecting pieces is conducted, wherein installation of the Z-shaped connecting pieces comprises line drawing, drilling, connecting piece installation and temporary connecting piece fixing; S3, installation of ECP wallboards is conducted, wherein the ECP wallboards are installed in a longitudinal and transverse installation mode; S4, board seams are adjusted; S5, welding of the Z-shaped connecting pieces is conducted; S6, sealant applying is conducted; and S7, repairing of the ECP wallboards is conducted. The ECP wallboards serve as non-structural decoration components, flexible connection is adopted during installation, the self-weight loads of the boards are borne by angle steel, and the horizontal loads are borne by the Z-shaped connecting pieces. During an earthquake, the boards can move in a staggered mode through gaps between the boards, and damage and falling which may occur due to mutual collision of the boards are avoided.
本发明公开了ECP墙板安装施工工法,包括以下步骤:S1:埋件、龙骨的放线与安装;S2:Z型连接件的安装:Z型连接件的安装包括画线、钻孔、安装连接件和临时固定连接件;S3:ECP墙板安装:ECP外墙板的按照纵向和横向安装形式进行安装;S4:调整板缝;S5:Z型连接件的焊接;S6:打密封胶;S7:ECP墙板的修补,ECP墙板作为非结构装饰构件,安装时采用柔性连接,板材自重荷载由角钢承担,水平荷载由Z型连接件承担。在地震时,板材可以通过之间的间隙错位移动,避免板材相互碰撞可能发生的破坏、脱落。
ECP wallboard installation construction method
The invention discloses an ECP wallboard installation construction method. The method comprises the following steps that S1, paying-off and installation of embedded parts and keels are conducted; S2, installation of Z-shaped connecting pieces is conducted, wherein installation of the Z-shaped connecting pieces comprises line drawing, drilling, connecting piece installation and temporary connecting piece fixing; S3, installation of ECP wallboards is conducted, wherein the ECP wallboards are installed in a longitudinal and transverse installation mode; S4, board seams are adjusted; S5, welding of the Z-shaped connecting pieces is conducted; S6, sealant applying is conducted; and S7, repairing of the ECP wallboards is conducted. The ECP wallboards serve as non-structural decoration components, flexible connection is adopted during installation, the self-weight loads of the boards are borne by angle steel, and the horizontal loads are borne by the Z-shaped connecting pieces. During an earthquake, the boards can move in a staggered mode through gaps between the boards, and damage and falling which may occur due to mutual collision of the boards are avoided.
本发明公开了ECP墙板安装施工工法,包括以下步骤:S1:埋件、龙骨的放线与安装;S2:Z型连接件的安装:Z型连接件的安装包括画线、钻孔、安装连接件和临时固定连接件;S3:ECP墙板安装:ECP外墙板的按照纵向和横向安装形式进行安装;S4:调整板缝;S5:Z型连接件的焊接;S6:打密封胶;S7:ECP墙板的修补,ECP墙板作为非结构装饰构件,安装时采用柔性连接,板材自重荷载由角钢承担,水平荷载由Z型连接件承担。在地震时,板材可以通过之间的间隙错位移动,避免板材相互碰撞可能发生的破坏、脱落。
ECP wallboard installation construction method
ECP墙板安装施工工法
CHENG JIANGHUAI (author) / HAN ANG (author) / LI YONGSHENG (author) / GUO JIAO (author) / BIAN HAIHONG (author)
2021-06-08
Patent
Electronic Resource
Chinese
Installation construction method of composite wallboard and composite wallboard
European Patent Office | 2022
|Fabricated wallboard installation structure and wallboard installation method
European Patent Office | 2020
|WALLBOARD INSTALLATION TOOL AND WALLBOARD INSTALLATION STRUCTURE
European Patent Office | 2023
|Assembly type prefabricated wallboard installation construction method
European Patent Office | 2020
|Building ALC wallboard construction and installation method
European Patent Office | 2024
|