Cast-in-situ bored pile construction process suitable for rock stratum area
The invention relates to a cast-in-situ bored pile construction process suitable for a rock stratum area. The cast-in-situ bored pile construction process comprises the steps that pile position lofting is conducted; a steel casing is buried; a drilling machine is in place for the first time, drilling operation is started, in the drilling process of the drilling machine, when deviation occurs, drilling is stopped, the drilling machine retracts upwards, and a pile hole is backfilled with stone of unit height; the drilling machine is in place again, drilling is conducted downwards, the depth of the drilling machine needs to be smaller than the height of the backfilled stone in the previous step, or drilling is conducted continuously till a drill bit deviates, and the drilling machine retracts again; the pile hole is backfilled with stone of unit height again, the steps are repeated for repeated impact drilling and stone backfilling, and drilling is conducted downwards continuously till the set hole depth is reached when deviation does not occur in the drilling process; sediment at the bottom of the hole is cleared out, and the hole forming quality is checked; a reinforcement cage is hoisted and placed, and a guide pipe is placed; concrete is poured; and the casing is pulled out, and pile forming quality inspection is conducted. According to the cast-in-situ bored pile construction process, the phenomenon of pile hole deviation can be improved, and the effect of high pile forming perpendicularity is achieved.
本申请涉及一种适用于岩层地区的钻孔灌注桩施工工艺,包括:桩位放样;埋设钢护筒;钻机初次就位,开始钻孔操作,钻机钻进过程中,当发生偏位时,停止钻进,钻机向上缩回,向桩孔内回填单位高度的石块;钻机再次就位,向下钻进,钻机深度须小于上一步骤中回填石块的高度,或持续钻进直到钻头发生偏位,钻机再次缩回;再次回填单位高度的石块,重复上述步骤进行反复冲击钻进和石块的回填,直到钻进过程中不会出现偏位时,向下连续钻进至设定孔深;清出孔底沉渣,检查成孔质量;吊放钢筋笼,并下导管;灌注混凝土;以及拔出护筒,进行成桩质量检验。其本申请能够改善桩孔偏位的现象,具有成桩垂直度高的效果。
Cast-in-situ bored pile construction process suitable for rock stratum area
The invention relates to a cast-in-situ bored pile construction process suitable for a rock stratum area. The cast-in-situ bored pile construction process comprises the steps that pile position lofting is conducted; a steel casing is buried; a drilling machine is in place for the first time, drilling operation is started, in the drilling process of the drilling machine, when deviation occurs, drilling is stopped, the drilling machine retracts upwards, and a pile hole is backfilled with stone of unit height; the drilling machine is in place again, drilling is conducted downwards, the depth of the drilling machine needs to be smaller than the height of the backfilled stone in the previous step, or drilling is conducted continuously till a drill bit deviates, and the drilling machine retracts again; the pile hole is backfilled with stone of unit height again, the steps are repeated for repeated impact drilling and stone backfilling, and drilling is conducted downwards continuously till the set hole depth is reached when deviation does not occur in the drilling process; sediment at the bottom of the hole is cleared out, and the hole forming quality is checked; a reinforcement cage is hoisted and placed, and a guide pipe is placed; concrete is poured; and the casing is pulled out, and pile forming quality inspection is conducted. According to the cast-in-situ bored pile construction process, the phenomenon of pile hole deviation can be improved, and the effect of high pile forming perpendicularity is achieved.
本申请涉及一种适用于岩层地区的钻孔灌注桩施工工艺,包括:桩位放样;埋设钢护筒;钻机初次就位,开始钻孔操作,钻机钻进过程中,当发生偏位时,停止钻进,钻机向上缩回,向桩孔内回填单位高度的石块;钻机再次就位,向下钻进,钻机深度须小于上一步骤中回填石块的高度,或持续钻进直到钻头发生偏位,钻机再次缩回;再次回填单位高度的石块,重复上述步骤进行反复冲击钻进和石块的回填,直到钻进过程中不会出现偏位时,向下连续钻进至设定孔深;清出孔底沉渣,检查成孔质量;吊放钢筋笼,并下导管;灌注混凝土;以及拔出护筒,进行成桩质量检验。其本申请能够改善桩孔偏位的现象,具有成桩垂直度高的效果。
Cast-in-situ bored pile construction process suitable for rock stratum area
一种适用于岩层地区的钻孔灌注桩施工工艺
2021-06-15
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Karst stratum cast-in-situ bored pile construction method
European Patent Office | 2020
|Cast-in-situ bored pile construction method under poor stratum
European Patent Office | 2024
|Soft soil stratum cast-in-situ bored pile construction device
European Patent Office | 2024
|Hole-forming construction method for cast-in-situ bored pile in hard rock stratum
European Patent Office | 2022
|Construction method of cast-in-situ bored pile for water-rich sandy stratum
European Patent Office | 2021
|