Tunnel vibration-free rolling construction technology
The invention discloses a tunnel vibration-free rolling construction technology. The tunnel vibration-free rolling construction technology comprises the steps of 1 preparing for construction; 2 carrying out surveying and setting out; 3 mixing an asphalt mixture; 4 transporting the asphalt mixture; 5 paving the asphalt mixture; 6 rolling the asphalt mixture; 7 treating a joint; and 8 carrying out detection. According to the tunnel vibration-free rolling construction technology, vibration road rollers are adopted for all compaction, and the rolling effect is enhanced; the problem that the tunnel height cannot meet the jacking height requirement of a common vehicle is solved by adopting a flat plate belt transport vehicle; three road rollers take a rest in turn, and drivers of the three road rollers stop to roll in turns every one hour; during construction, installed ventilation equipment is adopted for ventilation in a tunnel, and constructors are prevented from heatstroke; electric shock or misoperation is prevented, and necessary brightness of operation parts of electrical and mechanical appliances is guaranteed.
本发明公开了一种隧道无振碾压施工工艺,所述隧道无振碾压施工工艺包括以下几个步骤:步骤一:施工工作准备;步骤二:测量放样;步骤三:沥青混合料的拌制;步骤四:沥青混合料的运输;步骤五:沥青混合料的摊铺;步骤六:沥青混合料的碾压;步骤七:接缝的处理;步骤八:检测工作的进行。该隧道无振碾压施工工艺,所有压实采用震荡压路机,增强碾压的效果;采用平板皮带运输车解决了隧道高度满足不了一般车辆的顶起高度需要;采用三台压路机轮流休息,压路机司机每隔一小时,以停换三台轮换碾压;施工时隧道内采用已安装好的通风设备进行通风,避免施工人员中暑;防止触电或误操作,保证电气、机械器具的操作部分必要的亮度。
Tunnel vibration-free rolling construction technology
The invention discloses a tunnel vibration-free rolling construction technology. The tunnel vibration-free rolling construction technology comprises the steps of 1 preparing for construction; 2 carrying out surveying and setting out; 3 mixing an asphalt mixture; 4 transporting the asphalt mixture; 5 paving the asphalt mixture; 6 rolling the asphalt mixture; 7 treating a joint; and 8 carrying out detection. According to the tunnel vibration-free rolling construction technology, vibration road rollers are adopted for all compaction, and the rolling effect is enhanced; the problem that the tunnel height cannot meet the jacking height requirement of a common vehicle is solved by adopting a flat plate belt transport vehicle; three road rollers take a rest in turn, and drivers of the three road rollers stop to roll in turns every one hour; during construction, installed ventilation equipment is adopted for ventilation in a tunnel, and constructors are prevented from heatstroke; electric shock or misoperation is prevented, and necessary brightness of operation parts of electrical and mechanical appliances is guaranteed.
本发明公开了一种隧道无振碾压施工工艺,所述隧道无振碾压施工工艺包括以下几个步骤:步骤一:施工工作准备;步骤二:测量放样;步骤三:沥青混合料的拌制;步骤四:沥青混合料的运输;步骤五:沥青混合料的摊铺;步骤六:沥青混合料的碾压;步骤七:接缝的处理;步骤八:检测工作的进行。该隧道无振碾压施工工艺,所有压实采用震荡压路机,增强碾压的效果;采用平板皮带运输车解决了隧道高度满足不了一般车辆的顶起高度需要;采用三台压路机轮流休息,压路机司机每隔一小时,以停换三台轮换碾压;施工时隧道内采用已安装好的通风设备进行通风,避免施工人员中暑;防止触电或误操作,保证电气、机械器具的操作部分必要的亮度。
Tunnel vibration-free rolling construction technology
一种隧道无振碾压施工工艺
WANG GUOHUI (author)
2021-07-02
Patent
Electronic Resource
Chinese
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
Wireless Vibration Sensor for Tunnel Construction
British Library Conference Proceedings | 2006
|Vibration rolling device for super-surface pavement construction
European Patent Office | 2020
|Trans Tech Publications | 2012
|