Method for controlling bridge deformation in engineering of underneath passing high-speed railway bridge on road
The invention provides a method for controlling bridge deformation in a road underneath pass high-speed rail bridge project. The method comprises the steps: calculating the lengths of U-shaped grooves in a lower jacking section and a cast-in-place section of an existing high-speed rail bridge, the distance between a foundation pit and the existing high-speed rail bridge and the number and length of underground road protection piles on the two sides of the U-shaped grooves in the underneath pass range of the existing high-speed rail bridge; excavating a foundation pit in a layered mode, prefabricating a jacking section U-shaped groove structure, arranging a temporary U-shaped groove jacking rigid frame on the jacking section U-shaped groove structure, constructing a back pile, and installing a jack jacking system; while the foundation pit is excavated, constructing road protection piles; solidifying soil under a bottom plate of the U-shaped groove structure of the jacking section; gradually jacking the jacking section U-shaped groove in the direction of the existing high-speed railway bridge along the designed gradient, and excavating a soil body at the front end of the jacking section U-shaped groove while jacking is conducted; in the jacking process, dynamically controlling the ballasting measures; after the U-shaped groove of the jacking section is in place, constructing the U-shaped groove of the cast-in-place section; and gradually reducing the weight. The bridge pier abutment top deformation can be controlled to meet the new regulation requirement.
本发明提供了一种道路下穿高铁桥梁工程中控制桥梁变形的方法,计算既有高铁桥梁下顶进段及现浇段U型槽长度、基坑与既有高铁桥梁的距离、下穿既有高铁桥梁范围U型槽两侧的地面下道路防护桩的数量和长度;分层开挖基坑,预制顶进段U型槽结构,顶进段U型槽结构上设置临时U型槽顶刚架,施工后背桩并安装千斤顶顶进系统;开挖基坑的同时,施作道路防护桩;顶进段U型槽结构底板下度土体固化处理;将顶进段U型槽沿设计坡度逐步向既有高铁桥梁方向顶进,顶进段U型槽前端土体在顶进的同时挖除;顶进过程中,动态控制压重措施;顶进段U型槽就位后,施作现浇段U型槽;逐步减少压重措施。本发明可以控制桥墩台顶变形满足新规程要求。
Method for controlling bridge deformation in engineering of underneath passing high-speed railway bridge on road
The invention provides a method for controlling bridge deformation in a road underneath pass high-speed rail bridge project. The method comprises the steps: calculating the lengths of U-shaped grooves in a lower jacking section and a cast-in-place section of an existing high-speed rail bridge, the distance between a foundation pit and the existing high-speed rail bridge and the number and length of underground road protection piles on the two sides of the U-shaped grooves in the underneath pass range of the existing high-speed rail bridge; excavating a foundation pit in a layered mode, prefabricating a jacking section U-shaped groove structure, arranging a temporary U-shaped groove jacking rigid frame on the jacking section U-shaped groove structure, constructing a back pile, and installing a jack jacking system; while the foundation pit is excavated, constructing road protection piles; solidifying soil under a bottom plate of the U-shaped groove structure of the jacking section; gradually jacking the jacking section U-shaped groove in the direction of the existing high-speed railway bridge along the designed gradient, and excavating a soil body at the front end of the jacking section U-shaped groove while jacking is conducted; in the jacking process, dynamically controlling the ballasting measures; after the U-shaped groove of the jacking section is in place, constructing the U-shaped groove of the cast-in-place section; and gradually reducing the weight. The bridge pier abutment top deformation can be controlled to meet the new regulation requirement.
本发明提供了一种道路下穿高铁桥梁工程中控制桥梁变形的方法,计算既有高铁桥梁下顶进段及现浇段U型槽长度、基坑与既有高铁桥梁的距离、下穿既有高铁桥梁范围U型槽两侧的地面下道路防护桩的数量和长度;分层开挖基坑,预制顶进段U型槽结构,顶进段U型槽结构上设置临时U型槽顶刚架,施工后背桩并安装千斤顶顶进系统;开挖基坑的同时,施作道路防护桩;顶进段U型槽结构底板下度土体固化处理;将顶进段U型槽沿设计坡度逐步向既有高铁桥梁方向顶进,顶进段U型槽前端土体在顶进的同时挖除;顶进过程中,动态控制压重措施;顶进段U型槽就位后,施作现浇段U型槽;逐步减少压重措施。本发明可以控制桥墩台顶变形满足新规程要求。
Method for controlling bridge deformation in engineering of underneath passing high-speed railway bridge on road
一种道路下穿高铁桥梁工程中控制桥梁变形的方法
YOU GUANGJIE (author) / CAO QUAN (author) / WANG LU (author) / WANG YAN (author) / LI LI (author) / ZHOU JINBIN (author) / ZHAO YANFENG (author) / LIU XIANGQIONG (author) / GAO RONGHUI (author)
2021-07-09
Patent
Electronic Resource
Chinese
European Patent Office | 2024
|European Patent Office | 2023
|European Patent Office | 2023
|Jacking construction method and device for railway underneath passing frame structure bridge
European Patent Office | 2024
|