Cross construction method for converter installation and stokehole operation platform
The invention provides a cross construction method for converter installation and a stokehole operation platform. Firstly, a reinforced concrete platform is constructed on a stokehole feeding bay, a steel platform space is reserved on the reinforced concrete platform, fixing pieces are arranged on the periphery of the steel platform space, two buggy ladles in the stokehole feeding bay are connected to form a movable support table, then, a sliding rack is erected on the movable support table on the basis of the steel platform space, a furnace shell and a backing ring are sequentially hoisted to the sliding rack to form a set, the set is moved to the position above a converter base beside the movable support table for converter installation, converter installation is completed, a steel platform is installed in the steel platform space through the fixing pieces so as to form a complete stokehole operation platform together with the reinforced concrete platform.
本发明提供一种转炉安装与炉前操作平台的交叉施工方法,首先在炉前加料跨施工钢筋混凝土平台,并在钢筋混凝土平台上预留出钢平台空间,在钢平台空间的四周设置固定件,并对炉前加料跨中的两台钢包车进行连接形成移动支撑台,而后基于钢平台空间在移动支撑台上搭设滑移台架,将炉壳、托圈先后吊装至滑移台架上形成套组,并将套组移动至移动支撑台旁侧的转炉底座的上方以进行转炉安装,转炉安装结束,通过固定件在钢平台空间安装钢平台以与钢筋混凝土平台共同形成完整的炉前操作平台。
Cross construction method for converter installation and stokehole operation platform
The invention provides a cross construction method for converter installation and a stokehole operation platform. Firstly, a reinforced concrete platform is constructed on a stokehole feeding bay, a steel platform space is reserved on the reinforced concrete platform, fixing pieces are arranged on the periphery of the steel platform space, two buggy ladles in the stokehole feeding bay are connected to form a movable support table, then, a sliding rack is erected on the movable support table on the basis of the steel platform space, a furnace shell and a backing ring are sequentially hoisted to the sliding rack to form a set, the set is moved to the position above a converter base beside the movable support table for converter installation, converter installation is completed, a steel platform is installed in the steel platform space through the fixing pieces so as to form a complete stokehole operation platform together with the reinforced concrete platform.
本发明提供一种转炉安装与炉前操作平台的交叉施工方法,首先在炉前加料跨施工钢筋混凝土平台,并在钢筋混凝土平台上预留出钢平台空间,在钢平台空间的四周设置固定件,并对炉前加料跨中的两台钢包车进行连接形成移动支撑台,而后基于钢平台空间在移动支撑台上搭设滑移台架,将炉壳、托圈先后吊装至滑移台架上形成套组,并将套组移动至移动支撑台旁侧的转炉底座的上方以进行转炉安装,转炉安装结束,通过固定件在钢平台空间安装钢平台以与钢筋混凝土平台共同形成完整的炉前操作平台。
Cross construction method for converter installation and stokehole operation platform
转炉安装与炉前操作平台的交叉施工方法
GAO MINGJIN (author)
2021-07-27
Patent
Electronic Resource
Chinese
Stokehole modified steel slag and preparation method thereof
European Patent Office | 2021
|Steel box girder cantilever installation construction operation platform
European Patent Office | 2024
|Climbing type building construction operation platform outside building and installation method
European Patent Office | 2023
|