Building vibration isolation foundation construction method
The invention relates to the technical field of building construction, in particular to a building vibration isolation foundation construction method. The method comprises the following steps that S1, a foundation embedded part is optimized and manufactured; on-site preparation and paying off are carried out; a lower buttress is bound with a formwork; first-time pouring and fixing frame mounting are carried out; an embedded part is mounted; Second-time pouring concrete, third-time pouring and fourth-time pouring are carried out; a vibration isolator is mounted; an upper buttress is constructed; and checking and accepting are carried out. According to the construction method, the vibration isolator and the buttresses are integrally connected, so that the high-precision requirement of the plane position of the vibration isolator is met, the working procedures are detailed and perfect, the vibration isolation construction efficiency is remarkably improved, and the construction quality is guaranteed. The construction method is mainly applied to the construction aspect of the house-in-house vibration isolation foundation.
本发明涉及建筑施工技术领域,更具体而言,涉及一种建筑隔振基础施工方法。包括以下步骤:S1、基础预埋件优化及制作;现场准备及放线;下支墩绑紧支模;第一次浇筑及固定架安装;预埋件安装;第二~四次混凝土浇筑;隔振器安装;上支墩施工;检查验收。该工法通过将隔振器支墩整体连接,实现了隔振器平面位置的高精度要求,工序详尽完善,显著提高了隔振施工效率,保证了施工质量。本发明主要应用于房中房隔振基础施工方面。
Building vibration isolation foundation construction method
The invention relates to the technical field of building construction, in particular to a building vibration isolation foundation construction method. The method comprises the following steps that S1, a foundation embedded part is optimized and manufactured; on-site preparation and paying off are carried out; a lower buttress is bound with a formwork; first-time pouring and fixing frame mounting are carried out; an embedded part is mounted; Second-time pouring concrete, third-time pouring and fourth-time pouring are carried out; a vibration isolator is mounted; an upper buttress is constructed; and checking and accepting are carried out. According to the construction method, the vibration isolator and the buttresses are integrally connected, so that the high-precision requirement of the plane position of the vibration isolator is met, the working procedures are detailed and perfect, the vibration isolation construction efficiency is remarkably improved, and the construction quality is guaranteed. The construction method is mainly applied to the construction aspect of the house-in-house vibration isolation foundation.
本发明涉及建筑施工技术领域,更具体而言,涉及一种建筑隔振基础施工方法。包括以下步骤:S1、基础预埋件优化及制作;现场准备及放线;下支墩绑紧支模;第一次浇筑及固定架安装;预埋件安装;第二~四次混凝土浇筑;隔振器安装;上支墩施工;检查验收。该工法通过将隔振器支墩整体连接,实现了隔振器平面位置的高精度要求,工序详尽完善,显著提高了隔振施工效率,保证了施工质量。本发明主要应用于房中房隔振基础施工方面。
Building vibration isolation foundation construction method
一种建筑隔振基础施工方法
WANG KEXIN (author) / WANG TAO (author) / TIAN WENMAO (author) / FAN HUA (author) / CAO HUI (author) / LU XIAOPENG (author) / SUN XUESHUANG (author) / WEI JUN (author)
2021-09-03
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Equipment foundation vibration isolation construction method
European Patent Office | 2021
|Vibration isolation raft foundation, construction mold and construction method
European Patent Office | 2024
|LOCAL RESONANCE-TYPE BUILDING VIBRATION ISOLATION FOUNDATION
European Patent Office | 2023
|European Patent Office | 2022
|VIBRATION ISOLATION DAMPER AND VIBRATION ISOLATION STRUCTURE OF BUILDING FOUNDATION USING THE SAME
European Patent Office | 2020
|