A platform for research: civil engineering, architecture and urbanism
Construction method for prefabricated externally-hung wallboard
The invention discloses a construction method for a prefabricated externally-hung wallboard, and belongs to the technical field of prefabricated buildings. The construction method comprises the following steps that connecting angle steel in an upper connecting structure and a lower connecting structure is pre-mounted at a pre-embedded bolt through a locking nut in advance; meanwhile, vertical adjusting bolts are pre-mounted on adjusting embedded parts; during mounting, the prefabricated externally-hung wall panel is hoisted, the vertical adjusting bolts are abutted against frame beams of corresponding main body structures, the elevation of the prefabricated externally-hung wall panel is adjusted through the vertical adjusting bolts, and it is guaranteed that the position of the prefabricated externally-hung wall panel is accurate; then, transverse plates of the connecting angle steel in the upper connecting structure and the lower connecting structure are fixedly connected to the corresponding frame beams; and and finally, the locking nut is fastened to complete mounting. The construction method has the advantages of being simple in structure, safe, reliable and convenient to construct and mount on site.
本发明公开了一种预制外挂墙板的施工方法,属于装配式建筑技术领域,包括如下步骤:预先将上连接结构和下连接结构中连接角钢采用锁紧螺母预装到预埋螺栓处;同时将竖向调整螺栓预装到调整预埋件上;在安装时,吊装所述预制外挂墙板,使所述竖向调整螺栓抵靠于对应的主体结构的框架梁上,通过所述竖向调整螺栓调整所述预制外挂墙板的标高,保证所述预制外挂墙板位置准确无误;然后将所述上连接结构和所述下连接结构中的所述连接角钢的横板分别固接于对应的所述框架梁;最后紧固所述锁紧螺母,完成安装。本发明不仅结构简单、安全可靠,而且便于现场施工安装。
Construction method for prefabricated externally-hung wallboard
The invention discloses a construction method for a prefabricated externally-hung wallboard, and belongs to the technical field of prefabricated buildings. The construction method comprises the following steps that connecting angle steel in an upper connecting structure and a lower connecting structure is pre-mounted at a pre-embedded bolt through a locking nut in advance; meanwhile, vertical adjusting bolts are pre-mounted on adjusting embedded parts; during mounting, the prefabricated externally-hung wall panel is hoisted, the vertical adjusting bolts are abutted against frame beams of corresponding main body structures, the elevation of the prefabricated externally-hung wall panel is adjusted through the vertical adjusting bolts, and it is guaranteed that the position of the prefabricated externally-hung wall panel is accurate; then, transverse plates of the connecting angle steel in the upper connecting structure and the lower connecting structure are fixedly connected to the corresponding frame beams; and and finally, the locking nut is fastened to complete mounting. The construction method has the advantages of being simple in structure, safe, reliable and convenient to construct and mount on site.
本发明公开了一种预制外挂墙板的施工方法,属于装配式建筑技术领域,包括如下步骤:预先将上连接结构和下连接结构中连接角钢采用锁紧螺母预装到预埋螺栓处;同时将竖向调整螺栓预装到调整预埋件上;在安装时,吊装所述预制外挂墙板,使所述竖向调整螺栓抵靠于对应的主体结构的框架梁上,通过所述竖向调整螺栓调整所述预制外挂墙板的标高,保证所述预制外挂墙板位置准确无误;然后将所述上连接结构和所述下连接结构中的所述连接角钢的横板分别固接于对应的所述框架梁;最后紧固所述锁紧螺母,完成安装。本发明不仅结构简单、安全可靠,而且便于现场施工安装。
Construction method for prefabricated externally-hung wallboard
一种预制外挂墙板的施工方法
XU PENGQIANG (author) / LI FEI (author) / LI QINGTANG (author) / NING NANA (author) / LIN MENG (author) / DONG LIPING (author) / LI XIWEN (author) / LIU XIAOYAN (author)
2021-09-07
Patent
Electronic Resource
Chinese
Prefabricated externally-hung wallboard reinforcing structure
European Patent Office | 2022
|Prefabricated concrete externally-hung wallboard connecting device
European Patent Office | 2020
|Multilayer concrete composite prefabricated externally-hung wallboard
European Patent Office | 2022
|Prefabricated concrete externally-hung wallboard system and construction method thereof
European Patent Office | 2021
|