Elevator shaft foundation pit side wall cushion layer integral pouring structure and construction method
The invention relates to an elevator shaft foundation pit side wall cushion layer integral pouring structure and a construction method. The elevator shaft foundation pit side wall cushion layer integral pouring structure comprises a shaping formwork and a connecting and positioning piece, the shaping formwork is arranged in a foundation pit, and a pouring space is formed between the shaping formwork and the foundation pit; the connecting and positioning piece is arranged in the pouring space, a mounting hole is formed at one side of the connecting and positioning piece, and a first connecting rod is detachably connected into the mounting hole; and the free end of the first connecting rod penetrates through an insertion through hole formed in the side wall of the shaping formwork and is exposed out of the inner side of the shaping formwork. The invention discloses the construction method for integral pouring of an elevator shaft foundation pit side wall cushion layer. The construction method comprises the steps of foundation pit excavation, connecting and positioning piece installation, shaping formwork manufacturing and installation, concrete pouring, formwork removal and the like. Positioning of the shaping formwork and connection of the shaping formwork and a foundation pit are achieved. When the shaping formwork is disassembled, the shaping formwork and the foundation pit can be disconnected only by pulling out the first connecting rod. The shaping formwork is convenient to disassemble and does not need to be damaged.
本申请涉及一种电梯井基坑侧壁垫层整体浇筑结构及施工方法。电梯井基坑侧壁垫层整体浇筑结构,包括定型模板和连接定位件;定型模板设置在基坑中,两者之间形成浇筑空间;连接定位件设置在浇筑空间中,连接定位件一侧设置安装孔,安装孔内可拆卸地连接有一第一连接杆;第一连接杆自由端穿过定型模板侧壁开设的插接通孔而露于定型模板的内侧。电梯井基坑侧壁垫层整体浇筑的施工方法,包括基坑开挖、连接定位件安装、定型模板制作及安装、混凝土浇筑以及模板拆除等步骤。本申请实现了定型模板的定位以及其与基坑的连接。拆卸定型模板时,只需要将第一连接杆拔出即可解除定型模板和基坑的连接;不仅方便定型模板的拆除,且不用对其进行破坏。
Elevator shaft foundation pit side wall cushion layer integral pouring structure and construction method
The invention relates to an elevator shaft foundation pit side wall cushion layer integral pouring structure and a construction method. The elevator shaft foundation pit side wall cushion layer integral pouring structure comprises a shaping formwork and a connecting and positioning piece, the shaping formwork is arranged in a foundation pit, and a pouring space is formed between the shaping formwork and the foundation pit; the connecting and positioning piece is arranged in the pouring space, a mounting hole is formed at one side of the connecting and positioning piece, and a first connecting rod is detachably connected into the mounting hole; and the free end of the first connecting rod penetrates through an insertion through hole formed in the side wall of the shaping formwork and is exposed out of the inner side of the shaping formwork. The invention discloses the construction method for integral pouring of an elevator shaft foundation pit side wall cushion layer. The construction method comprises the steps of foundation pit excavation, connecting and positioning piece installation, shaping formwork manufacturing and installation, concrete pouring, formwork removal and the like. Positioning of the shaping formwork and connection of the shaping formwork and a foundation pit are achieved. When the shaping formwork is disassembled, the shaping formwork and the foundation pit can be disconnected only by pulling out the first connecting rod. The shaping formwork is convenient to disassemble and does not need to be damaged.
本申请涉及一种电梯井基坑侧壁垫层整体浇筑结构及施工方法。电梯井基坑侧壁垫层整体浇筑结构,包括定型模板和连接定位件;定型模板设置在基坑中,两者之间形成浇筑空间;连接定位件设置在浇筑空间中,连接定位件一侧设置安装孔,安装孔内可拆卸地连接有一第一连接杆;第一连接杆自由端穿过定型模板侧壁开设的插接通孔而露于定型模板的内侧。电梯井基坑侧壁垫层整体浇筑的施工方法,包括基坑开挖、连接定位件安装、定型模板制作及安装、混凝土浇筑以及模板拆除等步骤。本申请实现了定型模板的定位以及其与基坑的连接。拆卸定型模板时,只需要将第一连接杆拔出即可解除定型模板和基坑的连接;不仅方便定型模板的拆除,且不用对其进行破坏。
Elevator shaft foundation pit side wall cushion layer integral pouring structure and construction method
电梯井基坑侧壁垫层整体浇筑结构及施工方法
ZHU JIANGANG (author) / FANG BIN (author) / WEI CHENGGANG (author) / JIANG HONGLIANG (author) / NI JIANGANG (author)
2021-09-17
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
European Patent Office | 2023
|Deep foundation pit side wall concrete pouring construction structure and method
European Patent Office | 2021
|Cylinder formwork mechanism for elevator shaft and pouring method for elevator shaft
European Patent Office | 2020
|