Construction method of temporary support for concrete member dismantling operation
The invention discloses a construction method of a temporary support for concrete member dismantling operation, and relates to the technical field of building construction. The construction method aims to solve the problem that broken members are prone to falling in an existing dismantling method. The construction method comprises the steps that the dismantling section positions of concrete members are determined, and lines are drawn at planned cutting seams; paying-off positioning is conducted, specifically, a bottom plate is fixedly mounted under the to-be-dismantled concrete members, and temporary supporting structures are erected on the bottom plate and the concrete members; a cutting rope saw system is mounted at the line drawing position of each cutting seam, and cutting is started; after the two ends of any section are cut along the cutting seams, all the gravity of the section falls on the temporary supporting structure at the lower end, and the freely-cut section members are hoisted; and after the concrete members are all dismantled and hoisted, the temporary supporting structures are dismantled. Compared with the prior art, the construction method is more stable, the broken members do not fall, and the construction safety is high.
本发明公开了一种混凝土构件拆除作业临时支撑的施工方法,涉及建筑施工技术领域,为解决现有的拆除方法破碎构件易坠落的问题;本发明包括确定混凝土构件拆除分段位置,并在计划切割缝处画线;放线定位,在待拆除混凝土构件正下方固定安装底板并在底板与混凝土构件件搭设临时支撑结构;在每个切割缝画线处安装切割绳锯系统,开始切割;当任一分段两端沿切割缝画线切割完毕后,其全部重力落在下端的临时支撑结构上,吊运已切割自由的分段构件;待混凝土构件全部拆除并吊运完毕后,拆除临时支撑结构;本发明相比现有技术更加稳定,可以确保破除的构件不发生坠落事故,施工安全性高。
Construction method of temporary support for concrete member dismantling operation
The invention discloses a construction method of a temporary support for concrete member dismantling operation, and relates to the technical field of building construction. The construction method aims to solve the problem that broken members are prone to falling in an existing dismantling method. The construction method comprises the steps that the dismantling section positions of concrete members are determined, and lines are drawn at planned cutting seams; paying-off positioning is conducted, specifically, a bottom plate is fixedly mounted under the to-be-dismantled concrete members, and temporary supporting structures are erected on the bottom plate and the concrete members; a cutting rope saw system is mounted at the line drawing position of each cutting seam, and cutting is started; after the two ends of any section are cut along the cutting seams, all the gravity of the section falls on the temporary supporting structure at the lower end, and the freely-cut section members are hoisted; and after the concrete members are all dismantled and hoisted, the temporary supporting structures are dismantled. Compared with the prior art, the construction method is more stable, the broken members do not fall, and the construction safety is high.
本发明公开了一种混凝土构件拆除作业临时支撑的施工方法,涉及建筑施工技术领域,为解决现有的拆除方法破碎构件易坠落的问题;本发明包括确定混凝土构件拆除分段位置,并在计划切割缝处画线;放线定位,在待拆除混凝土构件正下方固定安装底板并在底板与混凝土构件件搭设临时支撑结构;在每个切割缝画线处安装切割绳锯系统,开始切割;当任一分段两端沿切割缝画线切割完毕后,其全部重力落在下端的临时支撑结构上,吊运已切割自由的分段构件;待混凝土构件全部拆除并吊运完毕后,拆除临时支撑结构;本发明相比现有技术更加稳定,可以确保破除的构件不发生坠落事故,施工安全性高。
Construction method of temporary support for concrete member dismantling operation
一种混凝土构件拆除作业临时支撑的施工方法
ZHANG ZHANG (author) / YE MEIJUAN (author)
2021-10-29
Patent
Electronic Resource
Chinese
IPC:
E02D
FOUNDATIONS
,
Gründungen
Cantilever steel structure construction temporary support dismantling method
European Patent Office | 2023
|Dismantling device and construction method for railway temporary support
European Patent Office | 2021
|Temporary support limiting device for dismantling horizontal structure and construction method
European Patent Office | 2024
|Temporary support for dismantling urban viaduct in complex environment and dismantling method
European Patent Office | 2024
|